News
CDA Delays Decisions on Two Islamabad Mega Project Bids

By Mariam Khan
Real Estate Analyst
4 min read
The Capital Development Authority has not yet finalised financial bids for two major Islamabad developments, a proposed cricket stadium and the New Islamabad Convention, Exhibition and Expo Centre. Both bid processes have already opened, but neither has been formally accepted, with the authority directing further review before moving forward on either project.
The Stadium Bid and Its Location Problem
The lowest bid received for the stadium's structure and surrounding road network was Rs8.9 billion, opened on 19 July. CDA has asked its consultant to assess whether this price is reasonable before proceeding, and officials say further action depends on that assessment's conclusion. The stadium is planned for Zone III near Sector D-12, an area where CDA's own rules generally prohibit all types of construction. The authority maintains that sports and recreational facilities fall outside this general prohibition, a distinction that will likely remain relevant to how the project's approval is eventually justified and documented.
The Convention Centre's Escalating Cost
The lowest bid for the New Islamabad Convention, Exhibition and Expo Centre, opened on 4 August, came in at Rs37 billion, submitted by a China Construction Third Engineering Bureau led joint venture, well above the project's original PC-I estimate of Rs16 billion. The cost increase stems substantially from a revised design that added steel fabrication and a steel dome roof in place of the original reinforced concrete structure. Only two joint ventures, both led by Chinese companies, actually participated in the bidding process. Following the bid opening, the construction company reportedly offered to complete the project for Rs34 billion instead, and CDA officials have separately explored a preliminary estimate suggesting the cost could fall to around Rs25 billion if the project were exempted from import duties and other taxes.
Why This Project Carries a Fixed Deadline
NICEEC is being built specifically ahead of the Shanghai Cooperation Organisation summit due to be hosted in Islamabad in 2027, intended to serve as a flagship, world class venue for conventions, exhibitions, trade fairs and cultural events. The facility is planned near the Bhara Kahu Bypass in the Malpur area, roughly three kilometres from the existing Jinnah Convention Centre, and CDA had originally targeted an 18 month construction timeline once work begins. This fixed summit deadline is precisely why the current pause on finalising bids carries genuine schedule risk, every week spent on cost reasonability review is a week subtracted from an already tight construction runway.
What CDA's Own Process Shows About This Project's History
This delay is not the first pause this specific project has experienced. Earlier in the bidding process, the Prime Minister directed that a third party be engaged specifically for quality assurance, which itself pushed back the original bid receiving deadline before financial bids were eventually opened in August. The project's board level Project Management Unit was only formally approved mid year, meaning the current cost reasonability review is one link in an already extended chain of sequential approval steps.
What Remains Unresolved
Neither bid has been formally accepted, and CDA has not indicated a specific timeline for when either decision will be finalised. Given the stadium's location within a formally restricted construction zone and the convention centre's substantial cost overrun relative to its original budget, both projects face genuine scrutiny that extends beyond routine procurement review.
What This Means for Surrounding Development and Property
Both projects carry real potential effects on surrounding road infrastructure, commercial activity, and land demand once built, particularly given NICEEC's role anchoring a new institutional and hospitality corridor near Bhara Kahu Bypass. A delay in formally awarding either project pushes back the timeline for that development impact to materialise, and given NICEEC's fixed 2027 summit deadline specifically, continued delay in bid finalisation increases pressure on the eventual construction schedule. Property owners, developers, and businesses anticipating activity around either site should treat formal contract award, not the bid opening itself, as the genuine milestone confirming these projects are moving toward actual construction.