Dasu–Mansehra 765kV Transmission Project Faces Payment and Execution Challenges, Contractor Says

By Mariam Khan
Real Estate Analyst
3 min read
News

By Mariam Khan
Real Estate Analyst
3 min read
The contractor on the 765kV transmission line between the Dasu Hydropower Plant and Mansehra, Sinohydro, has raised concerns about outstanding payments, design approvals, land access and regulatory clearances, according to a report published on November 12, 2026. The concerns are the contractor's. They are not findings, and the reports we have seen do not include the response of the authorities responsible for the project. Dasu itself is built by the Water and Power Development Authority.
Sinohydro says about Rs1.494 billion and $146.677 million remain outstanding under various invoices. These are contractor-reported claims. They are not independently established liabilities, and the report does not say whether the authorities accept them. The amounts are in two currencies, and we do not add them together or convert them. The report as we have it does not say which invoices are involved, how long they have been outstanding or what the contractor wants done.
The contractor also points to design approvals, land access and regulatory clearances as affecting the work. The report does not say which approvals are pending, which land parcels are involved or which clearances are needed, so we do not describe them. Power sector policy is published by the Power Division.
It is not known how far the line has been built, what the delay to the schedule is, if any, or when the line is due. The headline of the report speaks of "serious execution challenges", but we do not know their size. This is a separate matter from other Dasu-related reports, such as the Senate's review and the inspection panel, and we do not link them. We make no finding on who is responsible.
A 765kV line is meant to carry power from Dasu to the grid, so delays could affect future transmission capacity and infrastructure development in northern Pakistan. The report does not say that any area will lose supply or that any development is affected, and no effect on property has been established.
Developers who plan projects that depend on new northern grid capacity should treat dates as uncertain until the authorities respond. The signals to watch are the government's reply to the claims, payment of the invoices, resolution of land and approval issues and a revised schedule for the line.
Compare D-12/1, D-12/2, D-12/3 and D-12/4 in Islamabad, including property prices, locations, plot options and buying considerations.
Explore houses for sale in I-10 under PKR 3 crore, compare 4 marla options, check sub-sector prices and understand what your budget can buy.
Discover how to evaluate Margalla-view apartments in E-11 Islamabad, compare floor premiums, check building quality and assess property prices before buying.
Explore E-7 Islamabad plot prices, live Milkiyat listings, asking rates per sq yd, FBR valuations, plot sizes and essential buying checks.