The Islamabad High Court (IHC) has directed the federal planning and finance ministries to arrange funding for the Bhong Interchange on the Multan–Sukkur Motorway within one month. According to the proceedings, Rs100 million had previously been released. The petitioner's lawyer told the court that about Rs1.7 billion is still required and that the contractor has already completed work worth Rs350 million using its own resources. The funding directive does not guarantee immediate completion.
The court has set a one-month deadline for the ministries to arrange funds. It has not itself provided the money, and the reports do not say what the court will do if the deadline passes. The ministries could meet the direction, ask for more time or challenge it. We therefore present the order as a direction to find funds and not as a funded project.
The Rs1.7 billion still required and the Rs350 million of work done by the contractor were stated by the petitioner's lawyer. The reports do not say whether the government or the National Highway Authority (NHA) accepted them. The only figure described as released is Rs100 million. Compared with that, the Rs1.7 billion still needed is about 17 times as large (our own calculation). We have not added the figures together, because the reports do not give the interchange's total cost.
The contractor has reportedly completed Rs350 million of work with its own resources, which is more than three times the Rs100 million released (our own calculation). The reports do not say whether the contractor has been paid or has slowed work. The reports do not give the reason for any delay in the project, and we have not assumed one.
An interchange connects a motorway to local roads, and without it access to a motorway can be limited. The reports do not describe the Bhong Interchange's expected traffic or its link to nearby towns, so the benefit is described in general terms only. The wider NHA programme and its deadlines are covered in NHA Updates Progress on Major Motorways.
Owners and businesses near the proposed interchange should not assume a completion date from the court order. Those thinking of buying land because of the project should wait for confirmed funding and a revised schedule. The signals to watch are whether the ministries arrange the funds within the month, any NHA statement on work resuming, and any further hearing. Notices are published by the NHA, the Ministry of Planning, Development and Special Initiatives and the Ministry of Finance.
LDA approves verified GPA-based plot transfers in LDA City, making property transactions easier for overseas Pakistanis through authorised representatives.
SBP raises the gemstone sector's export payment limit from 10% to 30%, giving exporters greater flexibility in managing international trade payments.
Pakistan's property files often trade like financial assets, but unclear ownership rights and weak disclosure can expose buyers to legal and investment risks.
Prime Minister Shehbaz Sharif targets Rs1 trillion in Apna Ghar housing loans within six months, urging banks to simplify financing requirements.