News
Pakistan Court Sets New Rule for Enhanced Compensation in Land Acquisition Cases

By Mariam Khan
Real Estate Analyst
6 min read
News

By Mariam Khan
Real Estate Analyst
6 min read
The Federal Constitutional Court has ruled that a landowner who accepted a Land Acquisition Collector's award without protest, and did not seek a reference under Section 18 of the Land Acquisition Act, 1894 within the prescribed period, cannot later claim enhanced compensation simply because other landowners subsequently secured a higher award. A three member bench, headed by Chief Justice Amin ud Din Khan and comprising Justice Ali Baqar Najafi and Justice Syed Arshad Hussain Shah, set aside judgments of the Lahore and Peshawar High Courts that had extended enhanced compensation to landowners in this position.
The matters before the court arose from land acquired under the Land Acquisition Act, 1894 for a range of public purposes, including construction of educational institutions, motorways, defence projects and a grid station. In each case, some landowners had challenged the original Collector's Award by filing a reference under Section 18 of the Act, and ultimately secured enhanced compensation, in some instances all the way up to the Supreme Court. Other landowners in the same acquisition either accepted the Collector's Award without objection or failed to invoke the statutory reference remedy within the prescribed period. These non objecting landowners then sought the same enhanced compensation benefit through applications before the Land Acquisition Collector, writ petitions, or execution proceedings, relying on the enhancement already granted to similarly placed neighbours. The Lahore and Peshawar High Courts had, in the judgments now set aside, either extended the enhanced compensation to these non objecting landowners, remanded the matters back to the Reference Courts, or treated them as decree holders entitled to execute the enhanced awards.
The judgment, authored by Justice Amin ud Din Khan, held that a landowner who accepted the Collector's Award without protest, or who failed to seek a reference under Section 18 within the prescribed period, or who did not otherwise pursue the remedies available in law, is not entitled as a matter of law to claim the benefit of enhanced compensation subsequently awarded to a different landowner in independent proceedings. The court found that such a claim finds no support in the scheme of the Land Acquisition Act, 1894, and is inconsistent with the legal doctrines of finality, waiver, acquiescence and election. The judgment further held that this outcome cannot be sustained on considerations of equity or parity, nor on Articles 25 or 187 of the Constitution, nor Order XLI Rule 33 of the Code of Civil Procedure.
The bench held that the Land Acquisition Act, 1894 constitutes a complete and self contained code governing the determination and enhancement of compensation, with the right to seek enhancement exclusively regulated by the statutory mechanism the Act itself provides. In the absence of express legislative authorisation, the court found it cannot create a substantive right allowing non objecting or non litigating landowners to claim the benefit of enhanced compensation awarded in proceedings to which they were never a party, since doing so would amount to judicial legislation defeating the scheme Parliament consciously enacted. The judgment stated plainly that the statute nowhere provides that enhancement obtained by one landowner through a reference automatically accrues to landowners who accepted the award without protest, and described this omission as a conscious legislative design rather than an accidental gap, distinguishing between those who challenge an award through the statutory mechanism and those who elect not to. The court added that judicial sympathy cannot override statutory command, particularly where doing so would introduce into the statute a remedy Parliament consciously chose to omit.
Section 18 of the Land Acquisition Act, 1894 sets out a landowner's right to require the Collector to refer a dispute over an award, whether concerning the measurement of land, the amount of compensation, or the persons entitled to it, to a Reference Court for formal determination, provided the person has not already accepted the award. This reference mechanism, and the prescribed time period within which it must be invoked, is the specific statutory pathway the court held is the only route to enhanced compensation, rather than any later, indirect route through a neighbour's separate, successful case.
The Federal Constitutional Court was established on 13 November 2025 through the Twenty Seventh Amendment to the Constitution of Pakistan, creating a dedicated apex forum for constitutional and public law matters, with appeals reaching it from the High Courts of Pakistan. Chief Justice Aminuddin Khan has led the court since its founding. As a newly established institution now hearing significant land acquisition and compensation matters, its rulings in this area, including the full judgment made available through the court's own official website, are likely to carry considerable weight in shaping how future compensation disputes are resolved nationally.
This ruling establishes a clear, practical rule for anyone whose land is or may be acquired for a public project, a motorway, a grid station, an educational institution, a defence project, or any similar government purpose. A landowner who disagrees with the Land Acquisition Collector's award must formally challenge it by seeking a reference under Section 18 within the prescribed statutory period. Simply accepting the award, or missing that window, and then waiting to see whether a neighbour with land in the same acquisition later secures a higher payout through litigation, is no longer, and per this ruling never was, a viable path to obtaining that same enhanced amount. Landowners currently facing land acquisition for any infrastructure project should treat the reference process as a decision to make immediately upon receiving the Collector's award, rather than a remedy to keep in reserve pending the outcome of other landowners' cases.
Pakistan plans to split SNGPL and SSGCL into six to eight entities, restructure gas operations and shift over Rs3 trillion in circular debt.
Hyderabad Development Authority plans to auction 991 plots despite revenue officials' objections over land ownership, unpaid dues and incomplete legal formalities.
A Special Branch survey found three in four checked government houses in Islamabad rented out or occupied by non-allottees, as 43,000 federal employees wait for official homes.
The Sindh High Court froze construction on Clifton's Nehr-i-Khayyam until January 2027. Residents say work has not stopped and are questioning a 46-storey tower nearby.