Hundreds of investors who sank their savings and in many cases their foreign remittances into Park View City Islamabad’s Overseas Block and Golf Estate did not get possession. They did not get development. What they got instead was a notification telling them that if they want to take possession of their own plots, they must first begin construction within 3 to 6 months on land that still has no electricity, no gas, and no water connection.
That notification, issued by Park View City management in mid-2024, was the spark that ignited a mass protest. But the fire had been building for years. And what is now being offered to many of these same investors a plot adjustment to H Block or other sectors, sometimes with additional top-up charges is not a solution. It is the continuation of a pattern that has cost investors crores, triggered a court order, and left Pakistan’s overseas community asking a question that deserves a direct answer: where exactly is our land?
The Overseas Block was launched in 2019–20 on a three-year installment plan. The first balloting took place in July 2022, followed by a second in October 2022, while possession was promised to be handed over in June 2023 but the society failed to deliver on that commitment.
Society management had explicitly promised possession of Overseas Block plots within six months of the launch. That promise was broken. Then it was rescheduled. Then broken again.
The possession event was rescheduled from December 1, 2023 to January 27, 2024. It was then announced again for May 31, 2024. As of mid-2025, affected investors are being contacted not with possession but with an offer to relocate their plots entirely.
What happened on June 3, 2024 at Park View City’s site office was not a routine complaint. It was a breaking point.
Hundreds of people who had bought plots in the Overseas Block and Golf Estate stormed Parkview City’s site office in Islamabad. They were infuriated over delayed possession that had now exceeded two years. Their frustration was fuelled by a notification issued by management that linked possession of their plots to the construction of houses.
The notification read:
“We are extremely humbled and happy to announce the possession of members who want to construct their house in Overseas Block, subject to terms and conditions. The letters have been issued to priority members who have completed their installment payment plan till June 30, 2023, and possession is being given on first come first serve basis.”
This notification sparked outrage among members who felt their hard-earned money was being ridiculed by a ludicrous policy. In audios and videos, people at a meeting with the CFO of Park View City at the site office can be heard denouncing the policy as insulting, cheating, and a scam, vowing not to invest in Parkview’s future projects.
At that meeting, the society’s own Chief Financial Officer made a statement that investors had long suspected but never heard confirmed officially.
During the meeting with aggrieved customers, CFO Mr. Ihsan admitted that Parkview City couldn’t concentrate on the development of the Overseas and Golf Estate blocks, diverting all its resources to develop the Downtown project. He said development work had started in January, so they would be able to deliver possession after some time. When pressed about the provision of essential amenities like electricity, gas, and water needed for construction, the CFO had no logical answer — further infuriating protesters who felt forced to begin construction without necessary facilities.
Let that sink in. The CFO of Park View City officially confirmed that the developer had deliberately deprioritised the Overseas Block and Golf Estate — blocks into which investors had collectively poured billions of rupees in favour of the Downtown commercial project. Resources were diverted. Commitments were shelved. And investors were being told to start building anyway.
Golf Estate was launched in 2021 as a luxury residential offering. Investors were told it would be ready for possession in 2023. It was not.
The adjustment to H Block raises several unresolved questions:
Is H Block within the CDA-approved Layout Plan? Park View City’s CDA-approved Layout Plan covers 1,067.90 Kanals. Investors being offered H Block adjustment have no independent confirmation that sufficient unencumbered plots exist within the approved LoP to absorb the overflow from the abolished Golf Estate and delayed Overseas Block simultaneously.
Why must investors pay extra? H Block plots are being priced at current market rates significantly higher than what investors paid in 2019–2022. Adjusting to H Block therefore requires a top-up payment from the investor. The investor who has already waited five years, watched their asset depreciate by one-third, and received no possession is now being asked to pay more.
Why is H Block a lesser offer? The Overseas Block was specifically developed with a dedicated entrance at Gate 3 on Malot Road, premium overseas-focused amenities, and a location identity central to its marketing and pricing. Golf Estate was positioned around the Margalla Mountain range as a serene block with lush landscapes. H Block carries none of these specific location promises. It is not an equivalent replacement.
The possession and adjustment crisis was not the only grievance investors were managing. In April 2025, a separate but deeply related scandal emerged.
Park View City came under fresh public scrutiny as residents and investors raised serious concerns regarding unexpected development charges. The growing discontent led to a series of protests where members came together to express frustrations against what they labelled as unjust and fraudulent property charges.
For many residents, the nightmare began four to five years after they had already constructed their homes and commercial buildings. Despite initial promises made during plot purchases that all costs were included, buyers were now receiving surprise notifications demanding hefty development charges:
These were not new buyers being informed of charges upfront. These were people who had already built their homes — who believed all dues had been cleared — who were now receiving surprise bills years after possession.
The Golf Estate block, launched in 2021 with a promised date of possession after two years in 2023, again left its commitment unmet. Park View City then made the decision to abolish the Golf Estate block entirely, merging it into the Overseas Block, asking customers to switch to the Overseas Block if they want earlier possession.
An entire block marketed to investors as a distinct, premium, golf course-adjacent location was quietly cancelled and absorbed into another block. The investors who paid for Golf Estate based on its specific location, its promised amenities, and its unique identity were now being told their block no longer exists as a standalone entity.
This is not a minor administrative restructuring. It is the deletion of a product that thousands of people paid for.
The numbers tell a devastating story:
Investors who bought a 5 Marla plot in Overseas Block for PKR 65 lakhs in 2020 have seen values plummet to approximately PKR 40 lakhs a loss of over one-third of their investment after four years of delays Investors in Golf Estate who paid PKR 60 lakhs for a 5 Marla plot have seen values fall to PKR 40–45 lakhs because the block exists only on paper
For overseas Pakistanis who remitted foreign exchange to fund these bookings, the losses are compounded by currency depreciation. The same investment made in US dollars in 2020 is now worth dramatically less in dollar terms even before accounting for the plot value decline.
Against this backdrop of failed possession, cancelled blocks, and collapsed valuations, investors are now being approached with what is being framed as an “adjustment opportunity” relocation of their plot to H Block or other available sectors within Park View City.
This framing needs to be challenged directly.
Owners are being given refunds in the form of vouchers which can be adjusted in the installments of other blocks — not monetary refunds. A voucher keeps your capital locked inside the same project, under the same developer, on terms you never agreed to at the time of booking.
The legal system finally intervened.
On May 23, 2025, the Islamabad High Court stopped Park View City from demanding extra development charges from plot holders. Justice Inam Amin Minhas of the IHC, while hearing the case, issued a notice to Aleem Khan, the owner of the society, directing him to submit a response within ten days.
The court also requested the Capital Development Authority to provide the sanctioned Layout Plan of the society a demand that is highly significant. It means the IHC itself wanted to verify whether the charges being demanded were grounded in an approved development framework.
The petition was filed by Qasim Chatha along with other allotters, challenging the notice served for collecting additional development fees. The court issued a stay order to the extent of the petitioners on the notice to collect additional charges from allottees.
This stay order is directly relevant to every investor being asked to pay top-up charges as part of a plot adjustment.
| Year | Event |
|---|---|
| 2019–20 | Overseas Block launched; possession promised within 6 months of launch |
| 2021 | Golf Estate launched; possession promised by 2023 |
| July 2022 | First balloting of Overseas Block |
| October 2022 | Second balloting of Overseas Block |
| June 2023 | Possession deadline missed; no delivery |
| December 2023 | Possession event postponed |
| January 27, 2024 | Possession rescheduled again |
| May 31, 2024 | Possession re-announced for May 31 |
| June 3, 2024 | Hundreds storm site office; CFO admits resources diverted to Downtown |
| 2024 | Golf Estate block abolished; investors asked to switch to Overseas Block |
| April 2025 | Mass protests over surprise development charges |
| May 23, 2025 | IHC issues stay order against extra development charges; CDA Layout Plan summoned |
| 2025–2026 | Plot adjustment to H Block now being offered to Overseas Block investors |
If you are among the investors being approached for a plot adjustment to H Block or any other sector, the following steps are not optional — they are essential.
1. Do not sign any adjustment document without independent legal review. Any transfer document you sign waives your claim to the originally booked plot. Have a registered property lawyer — not your agent — review every word before you put your name on anything.
2. Demand the CDA-verified plot number of the replacement plot. Not the block name. Not the sector. The specific plot number, its dimensions, and its confirmed status within the CDA-approved Layout Plan. Verify this independently with CDA directly.
3. Reject vouchers as a substitute for a cash refund. If you cannot receive the plot you booked, you are entitled to request full monetary restitution. A voucher adjustable in other blocks is not a legal refund — it is a financial instrument that keeps your money captive inside the same project.
4. Do not pay any top-up amount before getting written answers. Why can’t your original plot be delivered? What is the legal basis for the additional charge? Is the replacement plot free from encumbrance? Get these answers in writing before any payment.
5. Reference the IHC stay order. If you are being pressured to pay additional development charges as part of your adjustment, the Islamabad High Court’s May 2025 stay order against Park View City’s collection of extra development charges is directly relevant. Cite it. Share it with your lawyer.
6. File a formal complaint with CDA. The Capital Development Authority regulates Park View City as an approved housing society. You have the right to file a written grievance with CDA if your booked plot within the approved Layout Plan is not being delivered.
7. Connect with other affected investors. The June 2024 protest showed that collective action produces results — and produces official admissions — that individual complaints do not. Find and join investor groups of Overseas Block, Golf Estate, and Hills Estate buyers.
| Factor | Overseas Block / Golf Estate (Booked) | H Block (Being Offered) |
|---|---|---|
| Launch Year | 2019–2021 | Existing sector |
| Promised Possession | 2023 | Subject to adjustment terms |
| Dedicated Gate | Yes — Gate 3 (Overseas Block) | No |
| Location Identity | Margalla-adjacent / premium scenic | General residential sector |
| Overseas Amenities | Yes — specifically marketed | No |
| Current Market Value | Depreciated by ~33% | Priced at current rates |
| Top-Up Charge Required | — | Yes, in many cases |
| Block Still Exists? | Golf Estate abolished; Overseas Block delayed | Yes |
Q: What is the Park View City overseas block adjustment? It refers to the situation where investors who booked plots in the Overseas Block, Golf Estate, or Hills Estate are being offered relocation to H Block or other sectors because their originally promised plots have not been delivered — in some cases after more than five years.
Q: Was Golf Estate actually cancelled? Yes. Park View City abolished the Golf Estate block and merged it into the Overseas Block, asking Golf Estate investors to switch if they wanted earlier possession. No formal public announcement was made to the general investor market.
Q: Did the CFO of Park View City admit to diverting resources away from the Overseas Block? Yes. At the June 2024 protest meeting at the site office, CFO Mr. Ihsan confirmed that resources were diverted from Overseas Block and Golf Estate development to the Downtown project.
Q: Did the Islamabad High Court take action against Park View City? Yes. In May 2025, the IHC issued a stay order stopping Park View City from collecting additional development charges, issued a notice to owner Aleem Khan, and requested the CDA’s sanctioned Layout Plan.
Q: Can Park View City legally force me to accept H Block instead of my original plot? No. Plot adjustment is only valid as a voluntary, documented agreement. You retain the right to reject any adjustment offer and demand a full cash refund if your booked plot cannot be delivered.
Q: How much have investor values dropped? Investors who purchased 5 Marla plots in the Overseas Block for PKR 65 lakhs in 2020 have seen values decline to approximately PKR 40 lakhs — a loss of over one-third after five years of non-delivery.
Q: Is Park View City a legal society? Park View City holds CDA approval for its Layout Plan. The issues being reported are not questions of the society’s legal status, but of its management’s accountability to investors who paid in good faith against commitments that were not honoured.
Park View City’s management is framing the plot adjustment to H Block as an opportunity — a chance for investors to receive possession sooner, in a developed sector, with a fresh start. Do not accept that framing.
What is actually being offered is a transfer of the developer’s liability onto the investor’s balance sheet. You are being asked to absorb the financial consequences of a land shortfall you did not create, accept a lesser product than what you paid for, and pay additional money to make that lesser product yours.
The CFO admitted resources were diverted. The IHC confirmed the development charges were legally contested enough to warrant a stay order. The Golf Estate block was abolished without public accountability. Investment values have dropped by a third. And the Overseas Block — launched in 2019 with a six-month possession promise — still does not have gas, electricity, or water on the ground.
Before accepting any adjustment, signing any document, or paying any additional charge, get independent legal advice. Verify every plot claim with CDA. And remember: the right to what you paid for is not something that needs to be negotiated away.
This investigative report is published for investor awareness purposes. Milkiyat.com does not represent or advise any party in disputes with Park View City. Investors are strongly advised to consult a registered property lawyer before taking any action. Information is sourced from publicly reported events, court proceedings, and investor testimonies available in the public domain.
Milkiyat.com has published a fully sourced, sector-by-sector investigation into the possession crisis across five CDA sectors — E-12 (37 years), I-12, C-14, C-15 and C-16 — built entirely on Dawn, The News, APP, and CDA’s own records, with every figure hyperlinked and single-source estimates flagged. Happy to offer it for citation or syndication.
With the RDA declaring 293 schemes illegal and the CDA sealing 99 more, the era of selling undeveloped land is over. From July 1, 2026, the Green Property Certificate has become the only valid proof of ownership. If you are holding a file for a plot that doesn’t physically exist, you need to read this breakdown of the new regulatory landscape.