News
Sindh Orders Faster Construction of Karachi Yellow Line BRT and Jam Sadiq Bridge

By Mariam Khan
Real Estate Analyst
4 min read
Sindh Senior Minister Sharjeel Inam Memon directed authorities to accelerate construction of Karachi's Yellow Line BRT depot and complete remaining work on the second section of Jam Sadiq Bridge, chairing a review meeting attended by Transport Secretary Asad Zamin, Sindh Mass Transit Authority officials, World Bank representatives, and project consultants. Officials were told to monitor progress daily and improve coordination among departments, consultants, and technical teams.
This Is at Least the Fourth Time This Same Directive Has Been Issued
This specific instruction, expediting the Yellow Line depot and Jam Sadiq Bridge specifically, is not a new directive, and its repetition over more than two years is worth understanding clearly. Comparable meetings producing near identical instructions were held in August 2024, October 2024, and November 2024, each time reviewing the same depot and bridge components and each time directing officials to work on a day to day basis to remove delays. In October 2024, the minister stated the contractor had committed to completing the project within 18 months, a target that would have pointed to roughly April 2026. That this same acceleration directive is still being issued in September 2026, well past that original timeline, confirms the project has continued slipping despite repeated, similarly worded instructions to speed it up.
What the Yellow Line Project Actually Involves
The Sindh Mass Transit Authority's Yellow Line is Karachi's third Bus Rapid Transit service, a 21 kilometre dedicated corridor running from Dawood Chowrangi in Korangi through Jam Sadiq Bridge, Main Korangi Road, the FTC Interchange, Sharea Faisal, Shahrah-i-Quaideen, and Kashmir Road, integrating with the Red Line at Numaish. The project is being delivered with World Bank support and is intended to operate under a public private partnership model once complete, with reported project costs cited at different points between roughly 61 and 100 billion rupees.
Why the Bridge and Depot Specifically Keep Coming Up
The depot and Jam Sadiq Bridge components have repeatedly been singled out across these successive review meetings as the specific bottlenecks requiring acceleration, rather than the BRT corridor's other infrastructure packages. This consistent focus suggests these two elements have functioned as the project's most persistent points of delay throughout its construction, with utility shifting and relocation issues specifically flagged in at least one earlier session as a factor requiring priority resolution to keep the broader timeline on track.
What Remains Unconfirmed
No new, specific completion date was given alongside this latest directive, continuing a pattern where acceleration instructions have been issued without an updated, binding target date attached. Given the project's now multi year history of similar directives following one another without full completion, readers should treat this latest instruction as further pressure applied to an already delayed project rather than confirmation that a new, firm deadline will actually be met this time.
What This Means for Property and Development Along the Corridor
Major mass transit and bridge infrastructure of this kind can meaningfully improve connectivity and accessibility along the corridors it serves, with direct relevance for residential and commercial property, development activity, and general accessibility in the areas connected by the Yellow Line, including Korangi, Sharea Faisal, and the broader route toward Numaish. Given the project's documented, repeated pattern of missed informal deadlines despite multiple acceleration directives, property owners, businesses, and investors along the Yellow Line corridor should treat actual, physical completion of the depot and Jam Sadiq Bridge, rather than this latest ministerial directive, as the genuine indicator that the project's benefits are about to materialise.