A tenant guide to renting an office in D-12 Islamabad covering Markaz plazas, sizes, floors, rent benchmarks, approved use, agreements and a checklist.
Explore 1 bed apartment prices in Park View City Islamabad, including project comparisons, apartment sizes, price per sq ft, lake-facing views and buying options.
Explore apartments for sale in Park View City Islamabad, including 1, 2 and 3-bed units, project details, price comparisons, payment plans and buyer guidance.
A tenant guide to renting an office in F-10 Islamabad covering Markaz plazas, sizes, floors, rent benchmarks, approved use, agreements and a checklist.
Guide

By Laraib Noor
Real Estate Analyst
23 min read
Rates last reviewed: 5 November 2026.** Prices below are retail planning ranges drawn from dealer and market trackers published between late October and early November 2026, plus the Pakistan Bureau of Statistics (PBS) city survey for August 2026.
If you are about to order material for a house, the question you want answered is simple: what do cement, saria, bricks, sand and crush cost today? The answer is rarely a single number. A bag of cement can differ by Rs 100 or more between brands, saria is quoted differently by mills and dealers, and sand and crush are priced by the cubic foot, the trolley or the dumper depending on who you ask. This guide puts the November 2026 construction material rates in Pakistan in one place, shows how they differ between Islamabad, Lahore and Karachi, and explains how to turn them into a real budget.
If you want to see what these rates mean for your own plot, run your plan through the Milkiyat Construction Cost Calculator first. Then use the tables below to check your supplier's quotation, and read the sections on quantities and buying tips so that a low rate does not turn into a high bill later.
| Material | Unit | Typical range now | Notes |
|---|---|---|---|
| Cement (grey, OPC, major brands) | 50 kg bag | Rs 1,500 – 1,610 | Most major brands cluster around Rs 1,530 – 1,570 |
| Cement (SRC, sulphate-resistant) | 50 kg bag | Rs 1,540 – 1,680 | Usually Rs 40 – 100 above OPC |
| Saria / steel, Grade 60 | per kg | Rs 260 – 277 | Rs 260,000 – 277,000 per tonne; mill lists can sit at the top of the range |
| Saria / steel, Grade 40 | per kg | Rs 255 – 275 | Slightly below Grade 60 at most dealers |
| Bricks, first class (A-class) | per 1,000 | Rs 17,000 – 27,000 | Dealer and kiln quotes sit lower; PBS retail survey sits higher |
| Bricks, second class (B-class) | per 1,000 | Rs 11,500 – 15,000 | Suitable for internal partitions where engineer agrees |
| Sand (river / Chenab) | per cft | Rs 50 – 120 | Varies strongly by city, sand type and delivery |
| Crush (bajri) | per cft | Rs 80 – 195 | Sources disagree widely; get a written dumper quote |
Treat these as a starting point. The next sections explain what sits behind each number and why different websites show different figures for the same material.
Before the details, a few points that explain most of the confusion.
Retail versus wholesale versus ex-factory. A mill or plant list price is not the price you pay at your site. Dealer margin, loading and transport are added, and these differ by city and by order size.
Delivered versus ex-yard. A sand or crush rate quoted at the yard is lower than the same material delivered to your plot, especially in the hilly or distant parts of Islamabad and Rawalpindi.
Brand and grade. Cement has brand premiums, saria has grade and brand differences, and bricks come in classes.
Date. Prices moved noticeably through 2026. A rate page that has not been updated for several weeks can be out of date even if it carries today's date in the title.
Units. Cement is per bag, steel per kg or per tonne (and per "mann" of 40 kg in the market), bricks per 1,000, sand and crush per cft, per trolley or per dumper. Trolley and dumper sizes are not standardised, so always convert to cft before comparing quotes.
For these reasons, we give ranges rather than a single price and we flag where sources diverge. For an official reference point, the PBS publishes city-wise retail prices for building materials in its monthly and weekly price reports.
In early November 2026, grey OPC cement from the major brands is selling at roughly Rs 1,500 to Rs 1,610 per 50 kg bag. Market trackers that publish daily brand lists show most large brands in a narrow band around Rs 1,530 to Rs 1,570, with Maple Leaf at the upper end and some regional or lower-tier brands noticeably cheaper.
| Brand | Approx. price per 50 kg bag (OPC) |
|---|---|
| Maple Leaf | Rs 1,550 – 1,610 |
| DG Khan | Rs 1,520 – 1,580 |
| Bestway | Rs 1,540 – 1,565 |
| Lucky | Rs 1,530 – 1,560 |
| Fauji | Rs 1,530 – 1,560 |
| Cherat | Rs 1,530 – 1,560 |
| Pioneer / Kohat / Paidar | Rs 1,530 – 1,565 |
| Flying / Shaheen Flying | Rs 1,475 – 1,505 |
| Askari / Falcon | Rs 1,385 – 1,545 (wide spread between sources) |
Special types cost more. Sulphate-resistant cement (SRC) is typically priced Rs 40 to Rs 100 above OPC, with some brand lists showing SRC bags in the Rs 1,640 to Rs 1,680 range. White cement is sold in 40 kg bags and is far more expensive, roughly Rs 2,100 to Rs 2,420 per bag depending on brand.
The PBS survey for August 2026 recorded an average of about Rs 1,555 per bag across surveyed cities, with Lahore at about Rs 1,590, Islamabad at about Rs 1,532 and Karachi at about Rs 1,465. Regional supply matters here: northern plants serve Punjab and Islamabad, while Karachi has its own supply base, so the gap between cities can change from month to month. Cement is also noticeably dearer than a year ago, with 2025 market averages typically quoted in the Rs 1,350 to Rs 1,420 range.
A common contractor rule of thumb is 0.4 to 0.5 bags of cement per sq ft of covered area for a double-storey grey structure. At about Rs 1,550 per bag, that is roughly Rs 620 to Rs 775 of cement per sq ft. For a 5 marla house of about 1,900 sq ft, planning bands of 750 to 950 bags mean about Rs 11.6 to Rs 14.7 lakh in cement alone.
Steel is the most volatile of the big-ticket materials. As of the first days of November 2026, branded Grade 60 deformed bars are being quoted by most dealer-tracking sites at about Rs 260 to Rs 265 per kg, which is Rs 260,000 to Rs 265,000 per tonne. At least one mill-published list dated 30 October 2026 shows Rs 277 per kg for Grade 60 and Rs 275 for Grade 40, while a number of dealer lists for other brands sit around Rs 250 to Rs 263. In practice you should expect to see anything from the low Rs 260s to the high Rs 270s depending on the mill, the dealer and the size of the order.
| Item | Rate now (approx.) |
|---|---|
| Grade 60 saria, per kg | Rs 260 – 277 |
| Grade 60 saria, per tonne | Rs 260,000 – 277,000 |
| Grade 60 saria, per 40 kg (1 mann) | about Rs 10,400 – 11,100 |
| Grade 40 saria, per kg | Rs 255 – 275 |
| Local / unbranded saria | Lower, but without documented quality (not recommended for structural work) |
Dealer lists in late October and early November 2026 place the common brands close together for Grade 60: Amreli, Mughal and Ittehad in roughly the Rs 258 to Rs 266 range, with Agha and some premium product lines a little higher. The differences between brands are usually small compared with the gap between a documented branded bar and an unbranded one.
City-level surveys for 2026 show Lahore at about Rs 258 to Rs 265 per kg, Karachi at about Rs 255 to Rs 263 and Islamabad and Rawalpindi at about Rs 260 to Rs 270 for Grade 60. These are indicative. Steel is a nationally traded commodity, and the main differences are freight and dealer margin.
Many dealers quote the same per-kg rate for 3 sutar (10 mm) and 4 sutar (12 mm) bars, with small differences for larger diameters. Always ask for the rate for the sizes in your structural drawings.
A practical planning band for a double-storey house is about 2.5 to 3.5 kg of steel per sq ft of covered area. At Rs 265 per kg, that is roughly Rs 660 to Rs 930 per sq ft. For a 5 marla house of about 1,900 sq ft, a planning band of 4,500 to 6,500 kg means about Rs 11.9 to Rs 17.2 lakh in steel.
Grade 60 is the usual choice for modern RCC work because it is stronger per kg, which can reduce the total tonnage in some designs. Your structural engineer decides the grade. Do not swap grades on site to save money, because the drawings and bar schedules assume a specific grade.
Brick prices are where sources disagree most, and the reason matters.
Dealer and kiln-based rate lists published in September and October 2026 show first-class (A-class, awwal) bricks at roughly Rs 16,000 to Rs 19,000 per 1,000 in Lahore and about Rs 17,000 to Rs 20,000 in Islamabad and Rawalpindi, with the twin cities running about 10 to 15 percent higher than Lahore for the same class. Second-class (B-class, doem) bricks sit at roughly Rs 11,000 to Rs 15,000 per 1,000.
The PBS retail survey for August 2026 shows higher figures, with first-class bricks at about Rs 23,355 per 1,000 in Lahore, about Rs 27,016 in Islamabad, about Rs 26,694 in Rawalpindi and about Rs 22,000 in Karachi. The survey average across the 32 cities that report a brick price was about Rs 18,517 per 1,000. The gap between kiln-gate quotes and retail survey prices reflects delivery, the class actually bought and local scarcity, and it is wide enough that you should always get a delivered, per-1,000 quote for the exact class you need.
| Brick class | Per brick (approx.) | Per 1,000 (approx.) |
|---|---|---|
| First class (A-class), dealer quotes | Rs 16 – 22 | Rs 16,000 – 22,000 |
| First class, PBS retail survey (Aug 2026) | Rs 22 – 27 | Rs 22,000 – 27,000 |
| Second class (B-class) | Rs 11.5 – 15 | Rs 11,500 – 15,000 |
A 9-inch brick wall uses roughly 9 bricks per sq ft of wall and a 4.5-inch wall about 4.5, before wastage. For a double-storey 5 marla house, planning bands of 50,000 to 65,000 bricks apply. At Rs 20 to Rs 27 per brick, that is about Rs 10 to Rs 17.6 lakh. Use first-class bricks for external and load-bearing walls, and discuss second-class bricks for internal partitions with your engineer.
Good first-class bricks have a uniform red colour, a clear ringing sound when two are struck together, sharp edges and low water absorption. Soak a sample in water for several hours; if it crumbles or absorbs a great deal of water, reject the lot before it is unloaded.
Sand is sold by the cubic foot, by the trolley and by the dumper. Trolley and dumper capacities vary by area, so convert every quote to a per-cft rate before comparing.
The most recent 2026 surveys we found put river or Chenab sand in Islamabad and Rawalpindi between roughly Rs 60 and Rs 120 per cft, with the higher figures in the September survey. Other 2026 sources show crush sand and hill sand at lower rates, from about Rs 65 to Rs 90 per cft. In Lahore, reported 2026 figures range from about Rs 50 to Rs 110 per cft, depending on whether it is Chenab or Ravi sand and whether the quote is ex-yard or delivered.
The PBS August 2026 survey recorded pit sand at about Rs 7,998 per trolley in Lahore, Rs 8,233 in Karachi and Rs 13,631 in Islamabad. That Islamabad figure is much higher than Lahore's, which is consistent with the cost of hauling sand to the capital, but remember that trolley sizes are not identical.
| Sand type | Typical use | Approx. rate per cft |
|---|---|---|
| Chenab / Ravi river sand | Concrete, plaster | Rs 55 – 120 |
| Crush sand | Masonry, budget work | Rs 65 – 90 |
| Hill sand | Masonry, northern areas | Rs 70 – 95 |
For a 5 marla house, planning bands are roughly 2,800 to 3,500 cft of sand; for a 10 marla house, about 5,500 to 7,000 cft. At Rs 90 per cft, that is about Rs 2.5 to Rs 3.2 lakh for a 5 marla house, so the exact rate matters, but not as much as cement or steel.
Crush, the coarse aggregate used in concrete, is priced by the cubic foot or by the dumper. The common types are Sargodha crush (often half-inch) and Margalla crush (often three-quarter inch), and in the twin cities Margalla crush is widely used because it is locally sourced.
Here too, sources diverge sharply. An August 2026 survey shows Margalla crush in Rawalpindi at about Rs 78 to Rs 95 per cft and Sargodha crush at Rs 70 to Rs 85. A September 2026 survey shows Sargodha crush in Islamabad and Rawalpindi at about Rs 170 to Rs 188 per cft and Margalla crush at Rs 178 to Rs 195. A Lahore-focused index shows crush around Rs 175 per cft with a very wide range. The most honest summary is that crush has been quoted anywhere between about Rs 80 and Rs 195 per cft in 2026, and the difference between those figures on 3,500 to 4,500 cft is large.
How do you deal with that? Ask each dealer for a written, delivered rate per cft for the specific crush type in your structural specification, specify the size, and check the load by measuring the dumper body before unloading.
| Material | Islamabad / Rawalpindi | Lahore | Karachi |
|---|---|---|---|
| Cement (OPC, 50 kg) | About Rs 1,530 – 1,580 (PBS Aug: about Rs 1,532 in Islamabad) | About Rs 1,550 – 1,600 (PBS Aug: about Rs 1,590) | About Rs 1,465 – 1,560 (PBS Aug: about Rs 1,465) |
| Saria Grade 60 (per kg) | Rs 260 – 270 (up to Rs 277 on some mill lists) | Rs 258 – 265 (up to Rs 277 on some mill lists) | Rs 255 – 263 |
| First-class bricks (per 1,000) | Rs 17,000 – 27,000 | Rs 16,000 – 23,500 | About Rs 22,000 (PBS Aug) |
| Sand (per cft) | Rs 60 – 120 | Rs 50 – 110 | Check locally (PBS Aug: about Rs 8,233 per trolley) |
| Crush (per cft) | Rs 80 – 195 | Rs 80 – 175+ | Check locally |
If you are comparing prices across cities as part of a decision about where to build or buy, the city pages on Milkiyat give you the property side of the picture: Islamabad, Rawalpindi, Lahore and Karachi.
Material rates matter only when you translate them into quantities. As a rule of thumb for a double-storey house, planning bands per 1,000 sq ft of covered area are:
| Material | Rough quantity per 1,000 sq ft | At today's rates (approx.) |
|---|---|---|
| Cement | 400 – 500 bags | Rs 6.0 – 8.0 lakh (at Rs 1,500 – 1,600) |
| Steel | 2,500 – 3,500 kg | Rs 6.5 – 9.7 lakh (at Rs 260 – 277) |
| Bricks | 25,000 – 35,000 | Rs 4.5 – 9.5 lakh (at Rs 18 – 27 each) |
These three together come to roughly Rs 17 to Rs 27 lakh per 1,000 sq ft, before sand, crush, shuttering, labour and contractor margin. Those quantity bands are consistent with the planning figures in Milkiyat's size-wise guides: about 750 to 950 bags of cement, 4,500 to 6,500 kg of steel and 50,000 to 65,000 bricks for a double-storey 5 marla house, and about 1,300 to 1,700 bags, 9,000 to 12,500 kg and 65,000 to 90,000 bricks for a 10 marla house.
To see how these ingredients combine into a per-sq-ft grey structure rate, compare them with the contractor rates in Milkiyat's guides on 5 marla house construction cost in Islamabad, Pindi and Lahore and the 20 marla house construction cost breakdown. For a deeper look at how cement and steel moved through the year, see our analysis of the 2026 construction cost crisis.
A practical check: if you buy materials yourself under a labour-only contract, add up the quantities and rates above. If you hire a contractor with material, compare the total with your own estimate. A quote far below your estimate may hide cheaper material; a quote far above should be explained line by line.
Several forces move the rates in this guide, and understanding them helps you time your purchases.
Energy and fuel costs. Cement and brick production are energy-intensive, and changes in fuel and power costs feed through to prices.
Exchange rate and imports. Steel and some cement inputs depend on imported raw material, so currency moves can change prices quickly.
Taxes and duties. Changes in taxes announced in the federal or provincial budgets can move retail prices.
Demand and season. Building activity picks up in the drier months, and demand spikes can push prices up. Many builders try to buy large quantities in the cooler, slower months, roughly November to February, when dealers are more willing to negotiate.
Freight and local supply. Sand, crush and bricks are heavy and cheap per unit, so transport is a large share of the delivered price. This is why Islamabad often pays more than Lahore for bricks and sand.
None of these can be predicted precisely, so build a contingency of 10 to 15 percent into any budget that depends on today's rates.
Material rates tell you what a build will cost; they do not tell you whether building is the right choice for you. A quick way to decide is to compare your estimated plot cost, grey structure, finishing and contingency against the price of a ready home in the same area.
On Milkiyat you can explore houses for sale in Islamabad, apartments for sale in Islamabad and plots for sale in Islamabad, then use the rates in this guide to estimate the cost of building on a plot.
Housing societies make the comparison easy to run. In Park View City Islamabad, for instance, you can look at plots for sale, estimate a construction budget using today's cement, steel and brick rates, and set the total against apartments for sale in the same society. When material prices are rising, a ready apartment can look more attractive than a house you have to build; when they are stable, building may come out ahead. Whichever society you consider, check its building rules, approval process and construction deadlines with the society management before you buy material.
If you would like local advice, browse verified property agents on Milkiyat or look at agencies. For newly launched developments, visit the new projects page. Builders and buyers who want to convert plot sizes into covered area before ordering material can use the Milkiyat Area Unit Converter, and those planning to finance a build can try the Home Loan Calculator.
In early November 2026, grey cement is selling at roughly Rs 1,500 to Rs 1,610 per bag, Grade 60 saria at about Rs 260 to Rs 277 per kg, first-class bricks at about Rs 17,000 to Rs 27,000 per 1,000 depending on the source, and sand and crush at widely varying per-cft rates. The pattern is clear: cement and steel are high but relatively stable at the moment, while bricks, sand and crush depend heavily on city, delivery and source. Use the ranges in this guide as a baseline, get written delivered quotes, keep a contingency, and re-check rates close to the date of purchase.
Start with the Milkiyat Construction Cost Calculator to turn rates into a budget, then explore listings across Islamabad and talk to a local agent if you are still deciding between building and buying.
In early November 2026, cement is about Rs 1,500 to Rs 1,610 per 50 kg bag, Grade 60 saria about Rs 260 to Rs 277 per kg, first-class bricks about Rs 17,000 to Rs 27,000 per 1,000 depending on the source, sand about Rs 50 to Rs 120 per cft and crush about Rs 80 to Rs 195 per cft.
Major grey OPC brands are being quoted at roughly Rs 1,500 to Rs 1,610 per 50 kg bag, with most clustering around Rs 1,530 to Rs 1,570. SRC is typically Rs 40 to Rs 100 higher, and white cement costs about Rs 2,100 to Rs 2,420 per 40 kg bag.
Branded Grade 60 saria is about Rs 260 to Rs 277 per kg, or Rs 260,000 to Rs 277,000 per tonne, depending on the mill and dealer. Most dealer lists in early November 2026 show Rs 260 to Rs 265.
The steel rate per kg for branded Grade 60 bars is about Rs 260 to Rs 277, with Grade 40 about Rs 255 to Rs 275. One mann (40 kg) of Grade 60 costs roughly Rs 10,400 to Rs 11,100.
First-class bricks are about Rs 17,000 to Rs 22,000 per 1,000 in dealer and kiln quotes, and about Rs 22,000 to Rs 27,000 in the PBS retail survey for August 2026. Second-class bricks are about Rs 11,500 to Rs 15,000 per 1,000.
Recent 2026 surveys put river or Chenab sand in Islamabad and Rawalpindi at roughly Rs 60 to Rs 120 per cft, depending on type and delivery. Compare quotes by cft, not by trolley.
Crush has been quoted from about Rs 80 to Rs 195 per cft in 2026, with Margalla and Sargodha crush priced differently. Because sources diverge, get a written, delivered dumper quote for the exact size you need.
Islamabad and Rawalpindi are typically around Rs 1,530 to Rs 1,580 for cement, Rs 260 to Rs 270 per kg for Grade 60 saria (some mill lists higher), and bricks about 10 to 15 percent above Lahore. See the city-wise table above for the full list.
Lahore is typically around Rs 1,550 to Rs 1,600 for cement, Rs 258 to Rs 265 per kg for Grade 60 saria, Rs 16,000 to Rs 23,500 per 1,000 for first-class bricks, and Rs 50 to Rs 110 per cft for sand.
Cement and steel are broadly similar, but bricks, sand and crush are usually dearer in Islamabad because of transport, so overall material cost is a little higher in the twin cities.
For a double-storey 5 marla house, cement, steel and bricks together cost roughly Rs 34 to Rs 50 lakh at today's rates, before sand, crush, shuttering, labour and margin. Use the Milkiyat calculator for a full estimate.
Tameeri samaan ka rate November 2026 mein taqreeban yeh hai: cement Rs 1,500 se Rs 1,610 per bori, saria Rs 260 se Rs 277 per kg, awwal eent Rs 17,000 se Rs 27,000 per 1,000, aur rait aur bajri ka rate shehar aur quality ke hisaab se kaafi mukhtalif hota hai. Khareedne se pehle tareekh ke saath likha hua delivered rate zaroor lein.
Cement and steel can change within days or weeks, while bricks, sand and crush change with season and local supply. Re-check rates before every large purchase.