11 min read
Building a house in DHA Karachi means dealing with three offices at once. DHA's Town Planning and Building Control directorate scrutinises the plan under DHA's own regulations. Clifton Cantonment Board takes its building fee and transfer tax and issues the completion certificate. The Military Estate Office takes its own payment and checks the land record. A single residential file needs payments to all three, seven sets of drawings and a site plan valid for two years.
DHA's rules sit on the building layer. Our guide on how to verify property in Karachi explains that every building must have an approved plan and a completion certificate, and in DHA both depend on DHA's regulations being followed from foundation to roof.
This guide explains DHA Karachi's building approval process, what the DHA Regulations 2020 allow on residential and commercial plots, the fees DHA publishes, the construction rules that catch owners out, and what buyers should check before paying for a DHA house or apartment.
The rulebook: DHA Regulations 2020
| Item | Detail |
|---|---|
| Full name | Pakistan Defence Officers Housing Authority Karachi Building Control and Town Planning Regulations 2020 |
| Approved by | DHA Executive Board, Special Meeting No. 2/2020, 19 August 2020 |
| Legal basis | Article 23 of President's Order No. 7 of 1980 |
| Applies to | All land in DHA Karachi's jurisdiction |
| Replaces | Earlier DHA regulations |
| Works alongside | Clifton Cantonment Board's building by-laws and the Cantonments Act 1924 |
The DHA Regulations 2020 are the detailed rulebook for DHA plots. Every plot must be used only for its allotted purpose.
Who does what in a DHA approval
| Office | Role |
|---|---|
| DHA Town Planning and Building Control | Scrutinises and approves the plan; site visits; completion survey |
| DHA Central Control Cell | Receives files and payments; returns approvals |
| Clifton Cantonment Board | Building fee, transfer of immovable property tax, sanction, completion certificate |
| Military Estate Office | Land payment and record check for lease or licence |
| Registered architect and engineer | Prepare and certify drawings and structural design |
Step by step: getting a residential plan approved
- Get the site plan from DHA. It is valid for two years.
- Pay three bodies: DHA, CBC (building fee and transfer tax) and the Military Estate Office.
- Prepare the file: DHA Form 1, the architect's certificate on DHA Form 2, CBC Forms A and B and undertaking, CNIC copies, a fresh transfer history letter from the first allottee to the current owner, and the lease or licence.
- Submit drawings: seven sets of the building plan (eight in Phase VIII), a CAD soft copy, and mechanical, electrical and plumbing drawings by a CBC-registered architect.
- Add indemnity bonds if you are building a basement or swimming pool.
- Lodge the case at the Central Control Cell, DHA head office.
- Respond to observations if the plan is returned.
- Collect the approval letter and drawings from the Central Control Cell.
Plots in Phase VII Extension, Khayaban-e-Saadi, Rizwan and Abbasi also need a commencement of building work order from DHA's Land Directorate.
DHA's published plan fees
DHA's checklist lists flat fees by plot size and processing speed, plus Rs2,500 in additional charges.
| Plot size | Members, ordinary (45 working days) | Members, urgent (37 working days) | Corporate bodies and foreigners, ordinary | Corporate bodies and foreigners, urgent |
|---|---|---|---|---|
| Up to 500 sq yd | Rs32,500 | Rs82,500 | Rs62,500 | Rs202,500 |
| Up to 1,000 sq yd | Rs52,500 | Rs127,500 | Rs77,500 | Rs302,500 |
| Up to 2,000 sq yd | Rs77,500 | Rs152,500 | Rs102,500 | Rs402,500 |
| Above 2,000 sq yd | Rs102,500 | Rs202,500 | Rs152,500 | Rs502,500 |
These are DHA's verification and plan fees as listed in its published checklist. CBC's building fee and transfer tax and the Military Estate Office's charges are paid separately. Confirm current amounts before applying.
Residential rules
| Plot size | Covered area | Open space (front, rear, side) | Floors |
|---|---|---|---|
| Up to 200 sq yd | 90% | Not specified | Basement, ground and one |
| 201 to 400 sq yd | 75% | 5 ft, 3 ft, 5 ft on the right side | Basement, ground and one |
| 401 to 700 sq yd | 65% | 10 ft, 5 ft, 5 ft | Basement, ground and one |
| 701 sq yd and above | 50% | 20 ft, 10 ft, 10 ft | Basement, ground and one |
| Height rule | Limit |
|---|---|
| Main building to roof | 22 to 32 ft |
| Ground and first floor internal height | 9 ft 6 in to 15 ft |
| Overall height with stair tower | 30 to 45 ft |
| Boundary wall | 8 to 10 ft |
Duplexes are prohibited. Plots of 401 square yards and above need a car porch of at least 10 by 14 feet and a grey-water tank, and must plant trees before completion. Swimming pools are allowed on plots of 500 square yards and above, subject to conditions.
Commercial rules
| Plot size | Covered area | Floor area ratio | Floors |
|---|---|---|---|
| Up to 250 sq yd | 100% | Not set | Basement, ground and four |
| 251 to 400 sq yd | 90% | Not set | Basement, ground and four |
| 401 to 600 sq yd | 85% ground, 75% upper | 1:5 | By floor area ratio |
| 601 to 999 sq yd | 80% ground, 70% upper | 1:5 | By floor area ratio |
| 1,000 to 1,999 sq yd | 75% ground, 65% upper | 1:5.5 | By floor area ratio |
| 2,000 sq yd and above | 70% ground, 65% upper | 1:5.5 | By floor area ratio |
Commercial buildings of basement, ground and four floors may rise to 69 feet without a lift or 84 feet with one; basement, ground and five floors to 82 or 97 feet. Lifts are required at a climb of 46 feet, with an additional lift above 59 feet. Ground and first floors are commercial, and flats above need a separate entrance.
Construction rules that catch owners out
| Rule | What it means |
|---|---|
| Basement walls next to built houses | Must be completed within 45 to 60 days of starting excavation |
| Retaining walls | Must be reinforced concrete |
| Indemnity bond | Required before a basement or pool is approved |
| Damage to roads, sewers or drains | Penalties and cost recovery |
| Excavation damage not remedied | Work can be stopped |
| Construction period | Two years from CBC sanction, extendable |
| Deviation from the approved plan | Needs DHA permission or a revised plan |
| Defaulting members | Services can be disconnected and penalties imposed |
Infrastructure in parts of DHA has come under strain as density has grown. Our report on the oil pipeline leak in DHA Karachi's Phase 6 shows why excavation and service lines are watched closely.
Completion and the occupancy certificate
| Step | What happens |
|---|---|
| Completion plan | Owner submits an as-built plan to DHA |
| Site survey | DHA's completion plan section inspects |
| No violations | DHA approves and sends the case to CBC, which issues the completion certificate |
| Violations | Owner removes them, or pays a penalty to regularise them |
| Penalty sharing | DHA pays 50% of the penalty to CBC as composition fees |
| Rebate | Planting trees earns a 25% rebate on the completion fee |
A house without a completion certificate cannot show that it was built as approved. Buyers of a finished DHA house should ask for the certificate before agreeing a price, since regularising violations later means a penalty and possibly removal work.
Building costs are also worth checking against official rules before construction starts. Our guide to house construction costs in Pakistan shows how covered area drives the budget.
DHA's 2020 rules vs CBC's 2007 by-laws
| Rule | CBC by-laws 2007 | DHA regulations 2020 |
|---|---|---|
| 401 to 700 sq yd covered area | 60% | 65% |
| 401 to 700 sq yd rear open space | 7.5 ft | 5 ft |
| Commercial up to 80 sq yd | Basement, ground and three | Up to 250 sq yd: basement, ground and four |
| Residential height | 33 ft above plinth | 22 to 32 ft to roof; up to 45 ft with stair tower |
The two rulebooks differ in places. For DHA plots, DHA applies its 2020 regulations in scrutiny, while CBC's by-laws govern its sanction and completion. Where they differ, ask DHA in writing which limit applies to your plot before finalising drawings.
What the numbers show: Milkiyat.com findings
Urgent processing costs about 2.4 times more to save eight working days. For a 1,000-yard plot: Rs127,500 ÷ Rs52,500 = about 2.4 times. The extra Rs75,000 buys 8 working days: about Rs9,375 per day.
Corporate bodies pay up to five times members' fees. Rs502,500 ÷ Rs102,500 = about 4.9 times for the largest plots on urgent processing.
A 500-yard house can have about 650 square yards of floors above ground. 500 × 65% = 325 square yards per floor × 2 floors = 650 square yards, or 5,850 square feet, plus a basement of up to 325 square yards.
DHA's 2020 rules allow 5% more cover than CBC's 2007 by-laws on mid-size plots. On a 600-yard plot: 600 × 5% = 30 square yards (270 square feet) more per floor.
The plan fee for a 500-yard plot is about Rs65 per square yard. Rs32,500 ÷ 500 = Rs65.
A file needs payments to three bodies and at least seven drawing sets. DHA, CBC and the Military Estate Office: 3 payments, and 7 sets of plans (8 in Phase VIII).
Checklist before you buy a DHA house
| Check | Where |
|---|---|
| Approved building plan matching the house | DHA Town Planning and Building Control |
| CBC completion certificate | Clifton Cantonment Board |
| No unregularised violations | DHA completion plan section |
| Basement or pool approved with indemnity | DHA |
| Transfer history from first allottee | DHA |
| CBC transfer tax and property tax paid | Clifton Cantonment Board |
Frequently asked questions
Q1. Who approves building plans in DHA Karachi?
A. DHA's Town Planning and Building Control directorate scrutinises and approves plans, with Clifton Cantonment Board sanctioning the building and issuing the completion certificate.
Q2. How long does DHA take to approve a house plan?
A. DHA's checklist lists 45 working days for ordinary processing and 37 for urgent processing.
Q3. What is DHA's building plan fee?
A. For members, DHA lists Rs32,500 for plots up to 500 square yards on ordinary processing, rising to Rs102,500 above 2,000 square yards. CBC and the Military Estate Office charge separately.
Q4. How many floors can I build on a DHA residential plot?
A. Basement, ground and one floor on all residential plot sizes under the 2020 regulations.
Q5. Are duplexes allowed in DHA?
A. No. The 2020 regulations prohibit duplexes.
Q6. Can I build a basement?
A. Yes, up to the ground floor footprint, with an indemnity bond, and basement walls next to built houses must be completed within 45 to 60 days of starting excavation.
Q7. Who issues the completion certificate?
A. Clifton Cantonment Board, after DHA's completion plan section has surveyed the house and cleared or regularised any violations.
This guide is for general information. DHA's regulations, fees and procedures change, and owners and buyers should confirm every rule, fee and approval with DHA Karachi, Clifton Cantonment Board and a registered architect before building or buying.