Looking for an office in F-8 Islamabad? See Markaz asking rents by size, rent per sq ft, new and furnished options and the lease checks to make before signing.
Buying in an FDA scheme? This guide explains which properties FDA transfers, the official document checklist, GPA, SPA and gift transfers, 2026-27 taxes for buyers and sellers, a worked tax example and each step from Ownership Clearance Certificate to transfer letter.
A possession plot lets you build now, while a non-possession plot gives you a right on paper and a wait. This guide explains both types in DHA Karachi, where each one sits, how prices compare and how to confirm a plot's real status.
Find 5 Marla plots for sale in A Block, Park View City Islamabad. Explore indicative prices, developer payment options, plot dimensions, location details and essential checks before buying.
Guide

By Laraib Noor
Real Estate Analyst
21 min read
Before a single brick is laid, every builder in Pakistan needs the same three numbers: how many cement bags, how many kilograms of steel and how many bricks the house will swallow. Get them wrong on the low side and the site stops while you wait for the next delivery. Get them wrong on the high side and you are left with leftover cement hardening in a corner and a stack of steel you paid for in advance. The tricky part is that the figures you find online disagree wildly. Cement for a 10 marla house is quoted anywhere from under 1,000 bags to over 2,000, and steel anywhere from about 5 tonnes to 19 tonnes.
This guide gives you realistic planning bands for a double-storey grey structure on a 5 marla, 10 marla and 1 kanal plot, explains why the published numbers differ, and shows you how to check your own contractor's bill of quantities. If you want a cost baseline for your project in rupees, start with the Milkiyat Construction Cost Calculator, then use the quantity bands below to understand what that money is buying.
The table below is for a standard double-storey house without a basement. It is a planning guide, not a structural bill of quantities.
| Item | 5 marla (about 1,900 sq ft covered) | 10 marla (about 3,300 sq ft covered) | 1 kanal (about 5,000 – 6,000 sq ft covered) |
|---|---|---|---|
| Cement (50 kg bags) | 750 – 950 | 1,300 – 1,700 |
| 1,900 – 2,600 |
| Steel (Grade 60) | 4,500 – 6,500 kg (4.5 – 6.5 tonnes) | 9,000 – 12,500 kg (9 – 12.5 tonnes) | 14,000 – 20,000 kg (14 – 20 tonnes) |
| First-class bricks | 50,000 – 65,000 | 65,000 – 90,000 | 100,000 – 130,000 |
| Sand | 2,800 – 3,500 cft | 5,500 – 7,000 cft | 9,000 – 12,000 cft |
| Crush (bajri) | 1,800 – 2,600 cft | 3,500 – 4,500 cft | 6,000 – 8,000 cft |
At the rule-of-thumb level, a double-storey house needs roughly 350 to 500 bags of cement, 2,500 to 3,500 kg of steel and 20,000 to 35,000 bricks for every 1,000 sq ft of covered area, with the brick figure at the lower end for larger houses because they have proportionally less wall per sq ft of floor.
Quantities only make sense if you know what they are based on. Ours assume:
A marla is 272.25 sq ft in the traditional system, but many housing societies and development authorities, particularly in Punjab, work with a 225 sq ft marla. That means a 5 marla plot is roughly 1,125 to 1,361 sq ft, a 10 marla plot roughly 2,250 to 2,722 sq ft and a 1 kanal plot (20 marla) roughly 4,500 to 5,445 sq ft. Check which unit applies to your plot, and use the Milkiyat Area Unit Converter to avoid mistakes.
Materials depend on built area, not plot area. A double-storey house builds on two floors, so its covered area is larger than the plot. We use about 1,900 sq ft for a 5 marla house, about 3,300 sq ft for a 10 marla house and 5,000 to 6,000 sq ft for a 1 kanal house, in line with common 2026 planning figures. If your design differs, scale the quantities in proportion to your covered area.
For a double-storey 5 marla house of about 1,900 to 2,000 sq ft, plan on roughly 750 to 950 bags of 50 kg cement. Most 2026 estimates fall between about 700 and 950 bags. A common contractor rule of thumb of 0.4 to 0.5 bags per sq ft gives about 760 to 950 bags for 1,900 sq ft, and one estimator for the twin cities shows about 930 bags for a typical 5 marla model.
Published figures far outside this band usually have an explanation. A number below 500 bags tends to leave out plaster, masonry mortar or one of the floors. A number above 1,000 bags usually reflects a larger covered area, a basement or a heavy slab design.
Cement goes into four places: concrete for foundations, columns, beams and slabs, mortar for brickwork, plaster on walls and the plinth or floor base. Concrete takes the largest share, followed by masonry and plaster.
For a double-storey 10 marla house of about 3,300 to 3,500 sq ft, plan on roughly 1,300 to 1,700 bags. A detailed 2026 quantity table for a 3,200 sq ft house shows about 1,220 to 1,410 bags, other widely used estimates are about 1,250 to 1,500 bags, and an Islamabad estimator uses about 1,616 bags. The 0.4 to 0.5 bag per sq ft rule gives about 1,320 to 1,650 bags for 3,300 sq ft.
Some guides quote 2,000 bags or more for a 10 marla house. Those are normally describing premium designs of 4,000 to 4,600 sq ft, houses with a basement, or models that include boundary walls and retaining structures.
A 1 kanal double-storey house usually has about 5,000 to 6,000 sq ft of covered area, and the planning band is 1,900 to 2,600 bags. Published figures range from about 1,600 to 1,800 bags on the lean side, to about 1,800 to 2,100 bags for a roughly 4,700 sq ft house, to about 2,240 to 2,600 bags for a 5,900 sq ft design, and up to about 3,000 bags in a very large, heavily specified model. Older guides that mention 1,600 bags were written when cement was a fraction of today's price and often assumed smaller covered areas, so use them with care.
Steel is the most expensive of the three materials and the one with the widest spread of estimates. For a double-storey 5 marla house, 2026 estimates range from about 4,900 kg to about 6,000 to 6,200 kg, with heavier A-grade Lahore designs going up to about 7,500 kg. A practical planning band is 4,500 to 6,500 kg of Grade 60 rebar, which is about 2.5 to 3.5 kg per sq ft of covered area.
Budget an extra 100 to 150 kg for binding wire, and allow for cutting and lap wastage on top of the theoretical quantity.
For a 10 marla double-storey house of about 3,300 sq ft, plan on 9,000 to 12,500 kg, or about 9 to 12.5 tonnes. A 2026 quantity table for a 3,200 sq ft house shows about 9 to 11.5 tonnes. An Islamabad estimator uses about 10.8 tonnes, and other builder guides give 12 to 14 tonnes for a heavier A-grade design. A premium 4,600 sq ft design is modelled at around 19 tonnes.
You will also find much lower figures, around 5.5 tonnes, in older guides. Those assume a lighter structure or different slab system and are not appropriate for a modern double-storey with RCC slabs on both floors. Binding wire for a house of this size is about 200 to 300 kg.
For a 1 kanal double-storey house, plan on 14 to 20 tonnes of Grade 60 steel. Several 2026 sources fall in the 16.5 to 21 tonne range for 5,900 to 6,000 sq ft designs, and one for a house of about 4,700 sq ft is naturally lower. Very low numbers of 4 to 5 tonnes, or about 9 tonnes, that appear in older and promotional pages are not realistic for a modern double-storey kanal house with RCC slabs and should not be used.
Typical estimates for a double-storey 5 marla house are about 50,000 to 63,000 first-class bricks, with a few calculators at 56,000 and others close to 79,000 for thicker walls and taller parapets. The planning band is 50,000 to 65,000 bricks, and up to about 79,000 if your design uses 9-inch walls throughout with heavy parapets.
For a 10 marla double-storey house, the planning band is 65,000 to 90,000 bricks. A detailed quantity table for a 3,200 sq ft house shows about 61,000 to 70,500 bricks, several widely repeated guides use about 85,000, and others go to 95,000 for thick walls and extra boundary work. The main driver is wall thickness: a 9-inch wall uses roughly 9 bricks per sq ft of wall, while a 4.5-inch wall uses about 4.5, before wastage.
A 1 kanal double-storey house typically needs 100,000 to 130,000 bricks. A 2026 calculator for a 5,900 sq ft house shows about 112,000 to 130,000, another for a similar size shows about 110,000 to 125,000, and older guides quote around 135,000 for a large double-storey house with a mumty. Some very large models go to about 160,000. If boundary walls and gatehouses are in the same contract, add them to the count.
Sand and crush are bulk materials priced by the cubic foot, and they add up quickly. For a 5 marla house, plan about 2,800 to 3,500 cft of sand and 1,800 to 2,600 cft of crush. For a 10 marla house, about 5,500 to 7,000 cft of sand and 3,500 to 4,500 cft of crush. For a 1 kanal house, about 9,000 to 12,000 cft of sand and 6,000 to 8,000 cft of crush. Those kanal figures are scaled from the smaller sizes, and published models range widely, with one 2026 estimator showing about 19,500 cft of sand for a very large kanal design.
Sand goes into concrete, mortar and plaster, so plaster-heavy designs use more. Crush goes only into concrete, so its quantity follows slab, beam, column and foundation volumes.
If your covered area does not match the sizes above, scale by area using these planning figures per 1,000 sq ft of a double-storey house:
| Material | Per 1,000 sq ft of covered area |
|---|---|
| Cement | About 350 – 500 bags |
| Steel (Grade 60) | About 2,500 – 3,500 kg |
| Bricks | About 20,000 – 35,000 |
| Sand | About 1,500 – 2,100 cft |
| Crush | About 950 – 1,450 cft |
Use the upper end for compact houses with a lot of internal partitions and heavy slab design, and the lower end for large, open plans. For example, a 2,400 sq ft house might need roughly 840 to 1,200 bags of cement and 6,000 to 8,400 kg of steel. These are rules of thumb. A structural engineer's drawings always overrule them.
When two guides give very different numbers for the same plot size, it is usually for one of these reasons.
Covered area. A "10 marla house" can mean 3,200 sq ft or 4,600 sq ft. That alone changes every number by more than 40 percent.
Number of floors and basement. A basement adds retaining walls, a thicker raft or footing and waterproofing, and pushes cement and steel up substantially.
Wall thickness and layout. Nine-inch external walls use roughly twice as many bricks per sq ft as 4.5-inch partitions, and houses with many small rooms have more internal wall.
Slab type. An RCC slab uses far more steel than an RB (reinforced brick) slab, which is why some older guides quote much lower steel for the same size.
Structural design. Column spacing, slab spans, double-height spaces, cantilevers and seismic detailing all change steel and concrete volume.
Inclusions. Some quantities include the boundary wall, mumty, water tank and septic tank, while others do not.
Age. Guides written years ago often mix old quantities with old prices, and their numbers should not be copied into a 2026 budget.
Here is a simple approach you can use to sense-check a contractor's numbers.
Step 1: Bricks. Measure the net wall area (excluding doors and windows) separately for 9-inch and 4.5-inch walls. Multiply 9-inch wall area by about 9 bricks per sq ft, and 4.5-inch wall area by about 4.5 bricks per sq ft. Add about 5 percent for breakage and wastage. For example, with 4,500 sq ft of 9-inch wall and 5,000 sq ft of 4.5-inch wall, bricks = 4,500 × 9 + 5,000 × 4.5 = 40,500 + 22,500 = 63,000, plus 5 percent, about 66,000. The wall areas here are illustrative, but the result lands in the 65,000 to 90,000 band for a 10 marla house.
Step 2: Mortar cement and sand. A 2026 calculator using Lahore prices estimates that 1,000 sq ft of 9-inch wall in 1:6 mortar takes about 10,600 bricks, 35 bags of cement and 263 cft of sand. Use that as a cross-check for the masonry share of your cement and sand.
Step 3: Concrete. Work out the concrete volume of foundations, columns, beams and slabs from the drawings. Cement, sand and crush then follow from the mix ratio, for example 1:2:4, with a wet-to-dry conversion factor of about 0.74 to account for volume loss when mixed. Your engineer's BOQ does this for you.
Step 4: Steel. Steel comes from the bar bending schedule in the structural drawings. If you do not have one yet, use 2.5 to 3.5 kg per sq ft as a placeholder and replace it once the drawings are ready.
Step 5: Add wastage. Typical allowances are about 5 percent for bricks and a few percent for cement, steel and aggregates, depending on how well the site is managed.
Putting prices on the quantities gives a feel for the material bill. At early-November 2026 market levels, cement is about Rs 1,550 per bag, Grade 60 steel about Rs 265 per kg and first-class bricks about Rs 20 to Rs 27 each. These rates move, so treat the result as indicative.
| House | Cement | Steel | Bricks | Three materials combined |
|---|---|---|---|---|
| 5 marla (1,900 sq ft) | Rs 11.6 – 14.7 lakh | Rs 11.9 – 17.2 lakh | Rs 10.0 – 17.6 lakh | about Rs 34 – 50 lakh |
| 10 marla (3,300 sq ft) | Rs 20.2 – 26.4 lakh | Rs 23.9 – 33.1 lakh | Rs 13.0 – 24.3 lakh | about Rs 57 – 84 lakh |
| 1 kanal (5,000 – 6,000 sq ft) | Rs 29.5 – 40.3 lakh | Rs 37.1 – 53.0 lakh | Rs 20.0 – 35.1 lakh | about Rs 87 lakh – 1.28 crore |
These figures exclude sand, crush, shuttering, labour and contractor margin. Steel is the biggest and most volatile line: on a 10 marla house, a Rs 15 per kg move in steel changes the bill by about Rs 1.4 to Rs 1.9 lakh. For a full cost view, read Milkiyat's size-wise guides, such as the 5 marla house construction cost guide for Islamabad, Pindi and Lahore and the 20 marla house construction cost breakdown.
Basement. A basement can add heavily to cement and steel because of retaining walls, a thicker raft or footings, waterproofing and extra excavation. There is no reliable one-size-fits-all adder, so ask your engineer for a separate BOQ line for the basement rather than scaling from the figures above.
Single storey. A single-storey house uses less material in total but more per sq ft, because foundations and plinth work are fixed costs. As a rough guide, the covered area of a single-storey 10 marla house is about 1,700 to 2,000 sq ft, and quantities scale down in proportion, with a slightly higher per-sq-ft figure for steel and cement.
Third floor or terrace rooms. Extra floors increase the load, which means heavier columns and foundations, not just more slab area. Tell your engineer now if you may add a floor later.
Boundary wall and mumty. Always check whether these are included, since they can add thousands of bricks and many bags of cement.
A BOQ is only useful if you check it. Look for these signals:
Be careful about stockpiling for the sake of a price move. Cement degrades with time and moisture, and large advance purchases lock up cash that you may need for other stages.
Once you know the material bill, you can compare the full cost of building (plot, grey structure, finishing, contingency and time) with the price of a ready house or apartment. For some families, building delivers the exact layout they want. For others, the effort of managing hundreds of bags of cement, tonnes of steel and tens of thousands of bricks is not worth it.
On Milkiyat you can explore houses for sale in Islamabad, apartments for sale in Islamabad and plots for sale in Islamabad, then use the quantities and rates in this guide to estimate what building on a plot would cost.
Housing societies make the comparison practical. In Park View City Islamabad, for example, you can look at plots for sale, work out the material bill for the house size you have in mind, and set the total against apartments for sale in the same society. Whichever society you consider, check its building rules, approval process and construction deadlines with society management before you order material.
If you would like local advice, browse verified property agents on Milkiyat or look at agencies. A good agent can tell you which neighbourhoods have easier site access for material trucks and what recent builders have actually used. For newly launched developments, see the new projects page, and for city-level context, the Islamabad, Rawalpindi, Lahore and Karachi city pages. If you plan to finance part of the project, the Milkiyat Home Loan Calculator shows the monthly impact.
For a double-storey house without a basement, plan on about 750 to 950 bags of cement, 4.5 to 6.5 tonnes of steel and 50,000 to 65,000 bricks for 5 marla, about 1,300 to 1,700 bags, 9 to 12.5 tonnes and 65,000 to 90,000 bricks for 10 marla, and about 1,900 to 2,600 bags, 14 to 20 tonnes and 100,000 to 130,000 bricks for 1 kanal. Use the per-1,000-sq-ft rules when your covered area differs, remember that basements, wall thickness and slab type can move the numbers significantly, and always let your structural engineer's drawings have the last word.
Start with the Milkiyat Construction Cost Calculator for a cost baseline, then explore listings across Islamabad and talk to a local agent if you are still deciding between building and buying.
A double-storey 5 marla house of about 1,900 to 2,000 sq ft typically needs about 750 to 950 bags of 50 kg cement, based on a rule of roughly 0.4 to 0.5 bags per sq ft.
A double-storey 10 marla house of about 3,300 sq ft needs roughly 1,300 to 1,700 bags. Larger, premium or basement designs can go above 2,000.
A double-storey 1 kanal house of about 5,000 to 6,000 sq ft typically needs about 1,900 to 2,600 bags.
About 4,500 to 6,500 kg of Grade 60 steel for a double-storey house, or roughly 2.5 to 3.5 kg per sq ft, plus about 100 to 150 kg of binding wire.
About 9 to 12.5 tonnes for a double-storey 10 marla house of around 3,300 sq ft. Premium designs of 4,000 sq ft or more can need considerably more.
About 14 to 20 tonnes for a double-storey 1 kanal house. Published 2026 estimates for 5,900 to 6,000 sq ft designs fall in the 16.5 to 21 tonne range.
About 50,000 to 65,000 first-class bricks for a double-storey house, and up to roughly 79,000 for thick walls and tall parapets.
About 65,000 to 90,000 bricks for a double-storey house, depending mainly on wall thickness and layout.
About 100,000 to 130,000 bricks for a double-storey house. Add more if boundary walls are part of the same contract.
As a rule of thumb for a double-storey house: about 350 to 500 bags of cement, 2,500 to 3,500 kg of steel and 20,000 to 35,000 bricks per 1,000 sq ft of covered area.
Beyond cement, steel and bricks, expect about 5,500 to 7,000 cft of sand and 3,500 to 4,500 cft of crush, plus binding wire, damp-proofing, anti-termite treatment, shuttering and rough electrical and plumbing materials.
Covered area, number of floors, basement, wall thickness, slab type, structural design and what is included in the scope all change the numbers. A "10 marla house" can mean anywhere from about 3,200 to 4,600 sq ft of built area.
Online calculators are useful for a first estimate, but they use average assumptions. Use them to get a baseline, compare the output with the bands in this guide, and rely on your engineer's BOQ for the final order.
Double storey ghar ke liye taqreeban 5 marla mein 750 se 950 bori cement, 4.5 se 6.5 ton saria aur 50,000 se 65,000 eenten; 10 marla mein 1,300 se 1,700 bori, 9 se 12.5 ton aur 65,000 se 90,000 eenten; aur 1 kanal mein 1,900 se 2,600 bori, 14 se 20 ton aur 1 lakh se 1.3 lakh eenten. Asal miqdar structural drawings se tay hoti hai.