PDA Building Plan Approval in Peshawar: Step-by-Step Process, Documents and Timelines

This guide covers building plan approval from the Peshawar Development Authority, not approvals from other authorities or Indian bodies that share the abbreviation PDA.
Who approves building plans in Peshawar?
Inside Peshawar Development Authority jurisdiction, the Building Control Agency approves building plans. The 2024 Regulations apply to all land, plots, buildings and houses in that jurisdiction. They say no building can be constructed, and no addition or alteration made, without the BCA's prior approval.
The penalty for skipping approval is serious. Work done without it can be removed at the owner's cost, and the owner can be charged up to five times the scrutiny fee. Approval also does not remove your own responsibility. The Regulations state that neither the permit nor PDA's inspections relieve the owner from building according to the rules.
What you need before you apply
Ownership and possession papers
For plots in PDA schemes such as Hayatabad and Regi Model Town, PDA asks for your allotment or transfer letter and your possession certificate. If you bought the plot but never took possession from PDA, get the plot demarcated and obtain the certificate first.
For land outside approved schemes, the Regulations ask for the revenue record of ownership attested by the Tehsildar, along with the aks-e-shajra. If you are unsure what each revenue paper proves, the guide to fard, intiqal and registry explains the difference.
A licensed architect and engineer
Drawings must be prepared by an architect registered with the Pakistan Council of Architects and Town Planners (PCATP). Structural drawings must come from an engineer registered with the Pakistan Engineering Council (PEC) where the building needs them. The architect signs Form 02, and the engineer signs Form 03. Larger plots and apartment buildings also need working drawings.
An energy code certificate
The 2024 Regulations added a requirement that older guides miss. Your file must include an ECBC 2023 compliance certificate. You can generate it online or submit a manual checklist showing how the design meets the energy code. Ask your architect to include it from the start, because a missing certificate is an easy reason for a query.
Documents checklist for a residential house
PDA's residential checklist and the Regulations list the following papers.
| Document | Copies | Notes |
|---|---|---|
| Form 01 (application) | Original | Signed by the owner |
| Form 02 | Original | Signed and stamped by the PCATP architect |
| Form 03 | Original | Structural engineer, where applicable |
| Proposed building plans | 4 sets | The Regulations also ask for one set on CD |
| Structural drawings | Original | Where applicable |
| Allotment or transfer letter | Attested copy | Proof of ownership |
| Possession certificate | Attested copy | From PDA |
| ECBC 2023 compliance certificate | Attested copy | Energy code |
| Owner's CNIC | Attested copy | Or the attorney's CNIC |
| Letter of amalgamation | Attested copy | Only if two plots were joined |
| Authority letter or power of attorney | Original | Only if someone applies for you |
| Owner's undertaking | Stamp paper | On PDA's prescribed format |
| Scrutiny fee | Pay order, bank draft or challan | Attached to the file |
Drawings must be on A0, A1 or A2 sheets. They should show plans, elevations, sections, a site plan with the north direction and road width, covered area calculations, plumbing and drainage, and the plinth and road levels.
Extra papers for commercial buildings
Commercial files need more. PDA's commercial checklist adds the full title documents (registry, intiqal, fard and aks-e-shajra), a right-of-way NOC where the plot is on a main road, a height NOC, a soil investigation report, a fire-fighting plan, a sewerage plan and a structural stability certificate. Irrigation and railway NOCs apply where relevant. Fuel stations need further NOCs from agencies such as EPA, OGRA and the district administration.
PDA building plan approval step by step
Step 1: Confirm ownership and possession
Check that your allotment or transfer is recorded with PDA and that you hold the possession certificate. Problems here stop the file at the first desk.
Step 2: Hire a licensed architect and engineer
Ask for their PCATP and PEC registration numbers. They will prepare the drawings, sign the forms and later certify construction stages.
Step 3: Collect the forms
Forms are available from the One Window Operation (OWO) counter or from PDA's website. You need Form 01 from the owner, Form 02 from the architect and Form 03 from the engineer.
Step 4: Pay the scrutiny fee
The Regulations require the scrutiny fee to be paid in advance, with a pay order, bank draft or challan attached to the file. PDA's own process sheet also mentions fee deposit slips issued after the scrutiny stage, so keep every receipt and ask the counter which payment is due at which point.
Step 5: Submit at the One Window counter
The OWO counter is in the PDA Complex, Phase 5, Hayatabad. Submit four sets of drawings with the forms and attested documents. The counter accepts the file only when every item on the checklist is present. For contact details, see PDA's head office and complaint channels.
Step 6: PDA checks the file
For a residential house, the BCA's internal process includes a site visit, scrutiny of the plans by the SDM and the Assistant Director of the BCA, and any observations sent back to the owner. Payments are then verified, and the file goes to the Deputy Director.
Step 7: Approval and signed drawings
The Deputy Director signs and stamps the approved drawings and gives the approval number. A copy is then uploaded to PDA's online system. Keep the approval letter and approved drawings safe, because you must display the permit and keep the drawings on site during construction.
Step 8: Build, inspect and complete
Your architect must inspect and report at set stages, such as demarcation, foundation, each roof slab and completion, and send the reports to the BCA within seven days. After construction, you must give notice of completion within one month and obtain a completion certificate before anyone occupies the building. The sewer connection application also needs that certificate.
How long does PDA map approval take?
PDA publishes a day-by-day internal process for residential buildings in Hayatabad. The table shows each step and its working days.
| Step | Working days |
|---|---|
| Application at the One Window section or online portal | 1 |
| Site visit report | 1 |
| Scrutiny of plans | 2 |
| Observation sent to owner, if any | 1 |
| Fee deposit slips and payment check | 1 |
| Case forwarded to Deputy Director | 1 |
| Signature, stamp and approval number | 1 |
| Upload to online system | 1 |
| Total of every listed step | 9 |
PDA states the total as 7 working days. The difference is the observation day, which applies only if the file has queries, and the upload day. Adding the other six steps gives 7, so a clean file with no observations should clear in about a week. PDA adds that the timeline works only when all prerequisite documents are complete and correct.
The Regulations set a longer legal limit. For residential plans submitted through a licensed architect, PDA must either convey approval or give written reasons for non-approval within 21 days of submission. Commercial plans get 60 days. PDA's commercial process sheet shows 15 working days, and its commercial committee meets every 15 days, so timing depends on the meeting date.
So plan for about one week if everything is in order, and allow up to three weeks before you worry.
PDA building plan approval fee in Peshawar
Fee figures need care, because PDA publishes them in several places. These are the ones found in official sources.
| Item | Published figure | Where it appears |
|---|---|---|
| Plan approval fee, residential | Rs 7 per sq ft of covered area | Khyber Pakhtunkhwa government PDA services page |
| Plan approval fee, commercial | Rs 14 per sq ft of covered area | Same page |
| Malba fee, Hayatabad, plots of 10 to 14 marla | Rs 18,000, one time for each map | Same page |
| Malba fee, Hayatabad, plots of 5 to 7 marla | Rs 12,000 | Same page |
| Malba fee, Hayatabad, one kanal | Rs 25,000 | Same page |
| Penalty for building before approval | Up to five times the scrutiny fee | PDA Building Control Regulations 2024 |
The malba fee covers moving and placing construction material in Hayatabad. Two items could not be confirmed. The Regulations refer to a scrutiny fee schedule (Annexure A) that was not available in readable form, and PDA's "Rates 2024 of Various Services" notice is a scanned image. Ask the OWO counter for the current schedule in writing before you pay.
Fees for transfer, possession and NOCs are separate from map approval. PDA's board approved higher rates for several of those residential fees in 2025, so do not reuse old receipts as a guide.
10 Marla House: Construction Timeline and Approval Fees
A marla is 272.25 square feet under the PDA Regulations, so a 10 marla plot is 10 times 272.25, which is 2,722.5 square feet. Your covered area depends on your design, so this example assumes 3,000 square feet of covered area. Replace it with your architect's figure.
| Item | Working | Result |
|---|---|---|
| Plan approval fee | 3,000 sq ft multiplied by Rs 7 | Rs 21,000 |
| Malba fee, Hayatabad, 10 marla | Published figure | Rs 18,000 |
| Published PDA fees in total | Rs 21,000 plus Rs 18,000 | Rs 39,000 |
| Time if the file is clean | PDA's stated total | 7 working days |
| Time if every step is used | Sum of listed steps | 9 working days |
| Legal limit for a decision | Regulations | 21 days |
Every extra 1,000 square feet of covered area adds Rs 7,000 to the plan approval fee. Architect and engineer fees, drawings and the ECBC certificate are paid separately and were not found in official sources, so they are not included.
Naqsha approval in Hayatabad and the rest of Peshawar
Many owners search for naqsha pass karwana Peshawar or naqsha approval Hayatabad. Both mean the same official process described above. PDA's published residential process sheet is written for buildings in Hayatabad, so the seven day figure is a Hayatabad figure.
PDA's Regulations apply across its whole jurisdiction, including Regi Model Town. If your plot is in another area, ask the OWO counter whether the same checklist applies. If you are not sure whether your plot is under PDA at all, confirm that first, because a plan approved by the wrong authority has no value.
Can I apply online?
The honest answer is "check first". PDA's own process sheet says applications go to the One Window section or an online portal, and the Khyber Pakhtunkhwa government portal lists an "Online Building Plan Approval" service. PDA announced a one-window online portal for building plans several years ago.
However, PDA's current E-PDA page says online applications are "coming soon", and the E-PDA app currently offers a plot search service. The 2024 Regulations still direct owners to submit files at the OWO counter in Phase 5, Hayatabad, and to take the forms from the counter or PDA's website.
For now, treat the counter as the reliable route. Call before you go and ask whether your type of file can be filed online.
After approval: validity and completion
An approved residential plan stays valid for 18 months. After that, a time extension is required, and it can be granted for up to two years. If you do not start work within the permitted time, PDA can charge "non-user charges".
PDA can cancel an approval if it was obtained through a false statement or misleading documents. If your finished building differs a lot from the approved plan, PDA may charge a double scrutiny fee for the completion plans. A building should not be occupied until the completion certificate is issued, and occupation without it can attract a monthly fine.
Additions, alterations and revised plans
You also need approval to change an existing building. The Regulations require an application on Form 01 for any structural alteration, for removing or rebuilding a roof or outer wall, for changing columns or beams, and for dividing a room or turning a passage into a room. A licensed architect or engineer must supervise the work.
A scrutiny fee for this type of work must be deposited with the BCA before renovation starts. If you change an approved plan, PDA may charge a revised fee. Two plots can be joined only if they are adjoining, side by side and approved by PDA, and the amalgamation letter must go into your file.
Common mistakes that delay naqsha approval in Peshawar
- Applying without a possession certificate or with unattested copies
- Using an architect or engineer who is not registered with PCATP or PEC
- Submitting fewer than four sets of drawings
- Leaving out the ECBC 2023 compliance certificate
- Forgetting the owner's undertaking on stamp paper
- Starting construction before approval, which risks removal of work and a penalty
- Changing the design on site without an approved revision
Buying a house or plot? Check the approved plan
If you are buying rather than building, ask the seller for the approved drawings and the completion certificate. Compare them with the building you see. Our guide to checking whether a Peshawar scheme is legal shows how to verify the scheme itself before you pay.
FAQs
How long does map approval take?
PDA states 7 working days for a residential file in Hayatabad when all documents are complete. Adding every listed step gives 9 working days. The Regulations allow up to 21 days for a decision on residential plans and 60 days for commercial plans. Missing papers restart the clock.
Which documents are needed?
You need Forms 01, 02 and 03, four sets of drawings from a PCATP architect, the allotment or transfer letter, the possession certificate, the owner's CNIC, an ECBC 2023 compliance certificate, an owner's undertaking on stamp paper and proof of the scrutiny fee. Plots outside schemes need attested revenue records and aks-e-shajra.
Can I apply online?
PDA's process sheet mentions an online portal, but PDA's E-PDA page still says online applications are coming soon. The 2024 Regulations send owners to the One Window Operation counter in Phase 5, Hayatabad. Confirm with PDA whether your file can be filed online before you rely on it.
What is the fee?
The Khyber Pakhtunkhwa government's PDA services page lists Rs 7 per square foot of covered area for residential plan approval and Rs 14 for commercial, plus a Hayatabad malba fee of Rs 18,000 for 10 to 14 marla plots. Confirm the current schedule at the counter.
What happens if I build without approval?
PDA-approved housing schemes in Peshawarcan order work stopped and can remove the construction at your cost. It can also charge up to five times the scrutiny fee. Some violations, such as building beyond the approved height or the plot limits, cannot be regularised at all, so always apply and wait for approval before you build.