Looking for an office in F-8 Islamabad? See Markaz asking rents by size, rent per sq ft, new and furnished options and the lease checks to make before signing.
Buying in an FDA scheme? This guide explains which properties FDA transfers, the official document checklist, GPA, SPA and gift transfers, 2026-27 taxes for buyers and sellers, a worked tax example and each step from Ownership Clearance Certificate to transfer letter.
A possession plot lets you build now, while a non-possession plot gives you a right on paper and a wait. This guide explains both types in DHA Karachi, where each one sits, how prices compare and how to confirm a plot's real status.
Find 5 Marla plots for sale in A Block, Park View City Islamabad. Explore indicative prices, developer payment options, plot dimensions, location details and essential checks before buying.
Guide

By Laraib Noor
Real Estate Analyst
27 min read
If you own a plot in Islamabad and want to build on it, there is one step you cannot skip, however eager you are to start digging: getting your building plan, what most people call the naqsha or map, approved by the Capital Development Authority (CDA). Construction without an approved plan can be stopped, penalised or demolished, and a house without a completion certificate can run into trouble when you try to sell it, connect services or mortgage it. The good news is that the process is well defined. The bad news is that the paperwork, the fee figures and the timelines are scattered across several CDA pages, and they do not always agree.
This guide puts the CDA building plan approval process in one place for 2026: who can apply, which documents you need, how the scrutiny fee works, how long approval takes, how the fast-track facilitation centre fits in, and what happens after approval, from plinth verification to the completion certificate. Before you start drawing, it is worth knowing what the construction itself will cost, so run your plot through the Milkiyat Construction Cost Calculator. Approval fees are small compared with building costs, but design choices such as a basement, extra floors or a large covered area affect both.
A quick note on sources. Everything below that concerns official requirements is taken from CDA's own Procedures and FAQ pages and from the Islamabad Capital Territory (ICT) Building Control Regulations 2020 as published in the Gazette of Pakistan. CDA can change fees and procedures without notice, and its own pages say so, so treat this guide as a checklist and confirm the current figures at the One Window Operation (OWO) before you pay anything.
| Item | What to know |
|---|
| Who approves | CDA's Building Control Directorate, with applications filed at the One Window Operation (OWO), Block-III, CDA Secretariat, G-7/4, Islamabad |
| Who must prepare the plan | A licensed architect (PCATP-registered) and a licensed structural engineer (PEC-registered), both licensed or enlisted with CDA |
| Main forms | Form A-1 (signed by the owner) and Form A-2 (signed by architect and structural engineer) |
| Fee | Scrutiny fee, paid in advance by pay order, plus any NOC processing fee. CDA's own pages publish two different per-sq-ft rates (see below) |
| Timeline | Three weeks (21 days) for houses and buildings up to 10,000 sq ft; six weeks above that; fast track at the facilitation centre reported at 2 to 3 days for an extra fee |
| Validity | Five years from the date of approval |
| After approval | Plinth and slab-level verification (Form D), stage inspections, notice of completion (Forms B-1 and B-2), completion certificate before occupation |
Building plans in Islamabad are governed by the Islamabad Capital Territory Building Control Regulations 2020, notified by CDA in December 2019 as S.R.O. 1575(I)/2019 and in force from 1 January 2020. CDA's public notices refer to these rules as amended in 2023, so always ask which version applies to your plot. The regulations apply to all private and public land and plots in the ICT, except the Diplomatic Enclave and other areas specifically excluded. That matters for buyers in private housing societies inside ICT limits, which we cover below.
Among other things, the regulations set out:
For your own copy, CDA lists its by-laws and regulations on its By-Laws & Regulations page, and a copy of the 2020 regulations as published in the Gazette is available in a PDF hosted by FGEHA. Ask your architect to design against the current version, including amendments.
CDA's Procedures page, its FAQ page and the 2020 regulations together give the following checklist. The two CDA pages differ slightly, for example on the number of copies of the plans, so where they disagree we say so and suggest you confirm at OWO.
| Document | Notes |
|---|---|
| Form A-1 | Application, signed by the allottee or attorney. Attested copy also required |
| Form A-2 | Signed by the approved architect and structural engineer, validated by CDA's Architecture Directorate |
| Building plans (architectural and structural) | The regulations call for six sets, plus one on CD. CDA's Procedures page also lists six copies, while its FAQ page lists four. Confirm at OWO |
| Scrutiny fee pay order | Paid through Estate Management, which issues the forwarding letter you file with the plan |
| Estate Management forwarding letter / NOC | Shows the scrutiny fee has been received. For residential buildings the NOC comes from Estate Management-I |
| Allotment letter or transfer letter | Attested copy |
| Possession certificate | Attested copy |
| CNIC of allottee, transferee or attorney | Attested copy |
| Sub-division letter | If your plot is a sub-divided portion |
| Letter of acceptance of attorney | If an attorney is applying |
| Contour plan | If applicable |
| Soil investigation report | If applicable |
| Indemnity bond | CDA's Procedures page lists an indemnity bond from the allottee, notarised, on Rs 30 stamp paper |
| Soundness and stability certificate and calculation book | Listed on CDA's Procedures page; prepared by the engineer |
Some third-party guides also mention property tax clearance and dues clearance. CDA's Estate Management and Revenue Directorates handle those, and unpaid dues can hold up your file, so check your plot's dues status before you file. If you need a refresher on property taxes in general, Milkiyat's Property Tax Info guide is a useful starting point.
The regulations list what the drawing set must include. Your architect will know the details, but it helps you to know what you are paying for:
Before spending money on drawings, confirm that your allotment or transfer letter and possession certificate are in order and that there are no outstanding dues with CDA. CDA also notes that transfers and approvals can be restricted where there are outstanding dues, a disputed title or a court stay, so a clean record saves time later.
CDA requires you to use a licensed architect and a licensed structural engineer, registered with the Pakistan Council of Architects and Town Planners (PCATP) and the Pakistan Engineering Council (PEC) respectively and issued a licence or enlistment by CDA. A list of licensed professionals can be obtained from OWO or the CDA Architecture Directorate. Beyond compliance, a good architect saves money: they know the setbacks, coverage and FAR for your plot and will keep your design within them.
Your architect prepares the plans in line with Schedule 1 of the regulations and your allotment terms. This is the stage to decide on a basement, the number of floors, the mumty and any future extension. Remember that the structural design and the covered area drive your material quantities. Milkiyat's guides on 5 marla and 20 marla house costs show how plot size affects the budget.
The scrutiny fee is paid in advance. The regulations require the pay order to be attached to the forms and plans, and the fee is calculated as per CDA's schedule. Estate Management issues the forwarding letter or NOC confirming receipt of the fee. For residential buildings, the NOC comes from Estate Management-I.
Under the regulations, your submission is organised in two folders:
File both at the OWO counter in Block-III of the CDA Secretariat. CDA's pages we reviewed describe submission at the OWO counter, and CDA lists online services at its CDA Online portal. CDA has announced plans for online building plan approval in the past, but we could not confirm that online submission of building plans is available at the time of writing, so check with OWO before assuming it is.
Estate Management forwards its NOC to the Building Control Section (BCS), which scrutinises the plans against the regulations and informs the architect and owner in writing, by approval, queries or refusal. The regulations say that after three weeks from submission the architect may contact OWO for information. If the plan is refused, the regulation requires the reasons to be given in writing.
Approval authority depends on the case. Under CDA's delegation of powers, residential house plans up to 500 sq yd are approved by the concerned Deputy Director, and larger ones by the Director Building Control. Important or large buildings, such as those above 10,000 sq ft or public buildings, can be referred to the Design Vetting Committee, which has a longer timeline.
Once approved, you receive the approval letter and stamped drawings. The regulations require a copy of the approval permit, drawings and specifications to be kept on site during construction. An approved plan remains valid for five years from the date of approval, after which revalidation or revised approval is required.
When foundations reach plinth (DPC) level, your architect certifies the plinth, plot size and building lines on Form D, submitted to Building Control with a copy to the Land Survey Division. Land Survey verifies the plot lines, plinth level and building lines within 15 days, and construction can continue after the provisional certificate is submitted. Form D must also be submitted at slab levels before pouring concrete. The point of this process is to catch layout errors early, when they are cheap to fix.
The regulations make architect inspections mandatory at specific stages, with reports submitted to OWO within seven days of each inspection. The stages include ground demarcation, basement foundation and roof level if applicable, ground floor at DPC level including the boundary wall, ground-floor roof before pouring the slab, first-floor roof height, any further floors, water tank and mumty, and completion.
Within one month of completing construction, the owner delivers a notice of completion on Form B-1, together with Form B-2 signed by the architect and the as-built drawings, to the OWO. We cover the completion certificate in detail below.
This is where most confusion arises, because CDA's two public pages publish different rates.
| Building type | CDA FAQ page | CDA Procedures page |
|---|---|---|
| Residential | Rs 1 per sq ft, minimum Rs 500 | Rs 3 per sq ft |
| Commercial, administrative buildings, public offices, foreign missions | Rs 2 per sq ft, minimum Rs 3,000 | Rs 10 per sq ft |
| Institutional, agro-farming, industrial | Minimum Rs 2,000 (as listed in the FAQ) | Not listed separately |
The regulations leave the rate to CDA's schedule and note that it may be revised from time to time, so the fee that applies to you is whatever Estate Management calculates on the day. As a guide to scale, a residential building of 3,300 sq ft covered area (a typical double-storey 10 marla house) would pay roughly Rs 3,300 at the FAQ rate and Rs 9,900 at the Procedures page rate. A 1,900 sq ft 5 marla house would pay about Rs 1,900 or Rs 5,700. These are small numbers, but remember that:
The regulations give CDA three weeks to decide on a residential plan. In late 2023, CDA's board approved a facilitation centre at the Building Control Directorate to shorten that for owners willing to pay extra. Press reports at the time described the terms as follows:
Those figures come from 2023 reports, such as Dawn's coverage of the centre's opening and The News report on the plan, and CDA may have changed the terms since. If you want fast-track approval, ask OWO or the Building Control Directorate for the current fee and eligibility. As a rough guide, a 5 marla or 10 marla plot falls under the 356 sq yd threshold in either marla definition, while a 1 kanal plot (roughly 500 sq yd or more) falls into the larger category.
The regulations set the standard timeline: within three weeks of receiving an application for a house or other building up to 10,000 sq ft covered area, CDA must either grant or refuse permission, specifying the provisions violated, or ask for further details. For buildings above 10,000 sq ft, the regulation allows six weeks, and important or public buildings and those above 10,000 sq ft can be referred to the Design Vetting Committee.
In practice, press reports in 2023 described the standard 21-day timeline as under pressure from staff shortages and heavy workloads, which is why the facilitation centre was created. Incomplete files are the most common reason for delay. In CDA's own 2026 releases on commercial building plans, for example, a number of cases were withdrawn before approval because documents were incomplete or prerequisites were not met. For a house, you can improve your odds by filing a complete set, using an architect who regularly deals with CDA, and responding to queries quickly.
Many buyers purchase plots in private housing societies inside Islamabad, and a common question is whether CDA or the society approves their plan. The short answer is that CDA's regulations apply to all private and public land in the ICT, including private housing schemes, but the process involves the society as well.
CDA's Forms & Applications page has a dedicated set of forms for private housing schemes within ICT limits. It lists the application for approval of plans (Forms A-1 and A-2), notice of completion (Forms B-1 and B-2), guidelines for approval and completion of building plans, a society NOC for approval and completion of building plans, an indemnity bond by the society's authorized representative and an indemnity bond by the plot owner. In other words, expect to obtain a NOC from your society and to file the CDA forms with it. CDA's 2020 revised modalities for private housing schemes also state that plot owners apply to the Building Control directorate for sanction of their building plans. Confirm the exact sequence with both your society and OWO before you file.
Three practical points:
The completion certificate, also called permission to occupy, is the final step, and it is easy to neglect once the house looks finished. The regulations say no building may be occupied or used, wholly or partly, without a completion certificate. Here is how to get it.
Who files and when. The owner delivers a notice of completion on Form B-1 within one month of completing construction. The architect signs Form B-2 together with the as-built (completion) drawings.
What to submit. CDA's pages list the documents as:
What CDA checks. After receiving the notice, the Building Control Section requests a site inspection and verifies the actual construction against the as-built plan. Items checked include the Form D certificates, maximum plinth level from the front road, ramp height, drainage grating at the gate, sewerage and storm-water connections to CDA mains (with a proper mechanical system for basements), mandatory setbacks, total covered area, emergency exits where applicable, firefighting arrangements for buildings of more than three storeys and additional water tanks for rainwater harvesting.
Then the certificate. If there is no change from the approved plan, or the changes comply with the regulations, and the fee and other requirements are met, the Deputy Director Building Control Section issues the completion certificate.
Penalties. The regulations impose a fine for occupying a building without a completion certificate. The gazetted text lists Rs 50,000 per year for residential buildings and Rs 100,000 per year for other buildings after the grace period of three months following the construction period, while other official references cite a monthly fine for residential buildings. Fine schedules have been amended before, so ask OWO what applies now.
The regulations are firm about this. Construction without prior approval can be stopped by written notice, the owner can be asked to show cause, and the unauthorised work can be removed or altered at the owner's cost, with or without notice in some cases. Construction that does not conform to the regulations is liable to demolition after 15 days' notice, and covered area in excess of the permitted limit must be demolished. In limited cases, deviations of up to five percent can be considered for compounding with charges if approved in advance and if they do not conflict with other rules. Oversight in scrutiny does not entitle you to violate the rules: the regulations say that an approval that overlooks a violation does not make the violation legal.
The practical lesson is simple: build what was approved, and if you want to change something significant, get a revised plan approved first.
Approval costs, including scrutiny fee, NOC processing, any fast-track fee and professional fees, are a small part of the total, but they come early and need to be planned. Once approved, you will need material, labour and contractors. For quantities, see Milkiyat's guides on how much cement, steel and bricks a house needs, and for current market prices, check rates before every large purchase. To work out financing, Milkiyat's tools include calculators that can help with planning.
Getting a plan approved, supervised and completed takes time, professional fees and patience. For some owners that effort is worth it for the exact layout they want. For others, a ready home avoids the whole process, because plans are already approved and, if you buy from a reliable source, a completion certificate may already exist for the building. Always ask for it when you buy a built property.
On Milkiyat you can browse houses for sale in Islamabad, apartments for sale in Islamabad and plots for sale in Islamabad, then weigh the cost and effort of building against buying.
Housing societies make the comparison concrete. In Park View City Islamabad, for example, you can look at plots for sale, estimate the cost of approval and construction using this guide, and set the total against apartments for sale in the same society. Whichever society you consider, ask for its approval documents and building rules, and verify the society's status with CDA before you pay.
For local advice, browse verified property agents on Milkiyat or look at agencies. A good agent can tell you which societies have a clear record of approvals and completion certificates, and which architects and contractors local buyers rely on. For city-level context, see Islamabad and Lahore on Milkiyat, and you can browse all Milkiyat blogs for more guides.
CDA building plan approval is a paperwork process, and paperwork rewards preparation. Hire a licensed architect and structural engineer, design to the regulations, file a complete set of Forms A-1 and A-2 with the scrutiny fee and title documents at the OWO, and expect a decision within three weeks, or sooner if you pay for the fast-track option. During construction, keep your Form D verifications and stage inspections up to date, and when the building is done, apply for the completion certificate before anyone moves in. Because CDA's fees and procedures can change without notice, and its own pages do not always agree, confirm the current figures at OWO before you pay.
Start with the Milkiyat Construction Cost Calculator to understand the build budget, then explore listings across Islamabad and talk to a local agent if you are still deciding between building and buying.
Hire a CDA-licensed architect and structural engineer, have them prepare the plans and sign Form A-2, sign Form A-1 yourself, pay the scrutiny fee through Estate Management, and file the forms, plans and title documents at CDA's One Window Operation in Block-III of the CDA Secretariat, G-7/4.
Forms A-1 and A-2, the building plans, the Estate Management forwarding letter showing the scrutiny fee was paid, the allotment or transfer letter, the possession certificate and a CNIC copy, plus sub-division, attorney, contour plan or soil report documents if applicable. CDA's Procedures page also lists an indemnity bond, a soundness and stability certificate and a calculation book.
The main fee is the scrutiny fee. CDA's FAQ page lists Rs 1 per sq ft for residential buildings (minimum Rs 500) and Rs 2 per sq ft for commercial (minimum Rs 3,000), while its Procedures page lists Rs 3 and Rs 10 per sq ft. Confirm the current rate at OWO. Other charges can include an NOC processing fee, a fast-track fee and your architect's and engineer's fees.
"Map approval fee" is the same scrutiny fee people usually mean when they say map or naqsha approval. See the fee table above and confirm the rate with Estate Management.
Naqsha is the Urdu word for the building plan or map. CDA naqsha approval means CDA's Building Control Directorate approving your architectural and structural drawings under the ICT Building Control Regulations 2020.
The regulations give CDA three weeks for houses and buildings up to 10,000 sq ft, and six weeks above that. A fast-track facilitation centre was reported in 2023 to approve small residential plans in about two days for an extra fee.
Yes, CDA set up a facilitation centre for fast-track approvals, which was reported in 2023 at an extra Rs 20,000 for residential plots up to 356 sq yd and more for larger buildings. Terms may have changed, so ask CDA for current details.
CDA has announced plans for online approval, and it lists online services at its CDA Online portal, but we could not confirm that building plans can be submitted online. Plan on filing at the One Window Operation unless CDA tells you otherwise.
Yes. The regulations make it mandatory to hire a licensed architect and a licensed structural engineer for the preparation of plans and for supervision until completion.
CDA's building control regulations apply to private land in the ICT, including private housing schemes, and CDA provides a set of forms for private housing schemes that includes a society NOC and indemnity bonds. Confirm the sequence with your society and with OWO, and make sure the society itself is CDA-approved.
Five years from the date of approval. After that, revalidation or revised approval is required.
It is the permission to occupy a building after construction. You apply with Form B-1 (owner) and Form B-2 with as-built drawings (architect) within one month of completion, and CDA inspects the building before issuing it. You must not occupy the building before you have it.
CDA can stop the work, require you to show cause, and remove or demolish unauthorised construction at your cost. Excess covered area must be demolished and penalties can apply.
The ICT Building Control Regulations 2020 are the regulations CDA applies, and CDA's public notices refer to them as amended in 2023. Ask your architect to confirm any later amendments that affect your plot.
CDA se naqsha manzoor karwane ke liye CDA-licensed architect aur structural engineer se plan banwayen, Form A-1 aur A-2 bharen, scrutiny fee ka pay order jama karwayen, aur tamam documents One Window Operation (OWO), CDA Secretariat G-7/4 mein dein. Aam tor par 21 din mein faisla hota hai, aur ghar ki tameer ke baad completion certificate lena zaroori hai.