Looking for an office in F-8 Islamabad? See Markaz asking rents by size, rent per sq ft, new and furnished options and the lease checks to make before signing.
Buying in an FDA scheme? This guide explains which properties FDA transfers, the official document checklist, GPA, SPA and gift transfers, 2026-27 taxes for buyers and sellers, a worked tax example and each step from Ownership Clearance Certificate to transfer letter.
A possession plot lets you build now, while a non-possession plot gives you a right on paper and a wait. This guide explains both types in DHA Karachi, where each one sits, how prices compare and how to confirm a plot's real status.
Find 5 Marla plots for sale in A Block, Park View City Islamabad. Explore indicative prices, developer payment options, plot dimensions, location details and essential checks before buying.
Guide

By Laraib Noor
Real Estate Analyst
28 min read
If you own a plot and are planning to build, the first number you will hear from every contractor is the grey structure rate per sq ft. It sounds simple, but in 2026 the same house can be quoted anywhere between Rs 2,800 and Rs 3,600 per sq ft, and sometimes more, depending on the city, the society, the steel brand and what the contractor has actually included. Cement and steel have both moved up sharply over the past two years, labour has followed, and most of the rate cards you find online are already out of date. This guide pulls the October and November 2026 market picture into one place so you can read a quotation with confidence.
Before going deeper, run your own plot through the Milkiyat Construction Cost Calculator. Enter your covered area, city and quality level and you will get a working budget in a minute. Then come back to this article to understand what sits behind that number, how the rate changes between Islamabad, Lahore and Karachi, how a "with material" contract differs from a "labour only" contract, and where owners usually lose money.
A quick note on how to read the figures in this article. Pakistan has no official, government-published grey structure rate. What you see below comes from public calculator outputs (including Zameen's construction cost calculator, updated mid-October 2026), builder rate cards published in Q3 and Q4 2026, and Milkiyat's own market tracking. Treat every range as a planning estimate, then confirm it with two or three written quotations for your specific drawings.
| Contract type | Typical rate per sq ft of covered area | Notes |
|---|
| Grey structure with material (Lahore) | Rs 2,800 – 3,500 | Standard A-grade, Grade-60 steel, major-brand cement |
| Grey structure with material (Islamabad & Rawalpindi) | Rs 3,200 – 3,600 | Standard spec; upper-spec and basement work can reach Rs 4,000+ |
| Grey structure with material (Karachi) | Rs 2,900 – 3,500 | DHA and Clifton premium work is quoted at Rs 3,500 – 4,000 |
| Labour-only grey structure (Lahore, Karachi) | Rs 550 – 850 | Owner buys all material |
| Labour-only grey structure (Islamabad, Rawalpindi) | Rs 700 – 1,000 | Roughly Rs 150 above Lahore |
For comparison, Zameen's calculator put double-storey grey structure with material at about Rs 2,762 to Rs 3,032 per sq ft for Lahore, Karachi and Islamabad in mid-October 2026. In our experience, calculator outputs tend to sit at the lower edge, while real contractor quotations land in the middle to upper part of the ranges above. We explain why further down.
Grey structure is the complete structural shell of a house, built up to the point where it is standing, roofed and plastered but not yet livable. It is called "grey" because everything you see is cement, concrete, brick and steel. If you are searching for what is included in grey structure, this is the usual scope:
The grey structure usually does not include tiles and flooring, paint, doors and windows, kitchen cabinets, wardrobes, false ceilings, electrical fixtures and switches, sanitary fittings, boundary wall finishing, main gate, elevation work, or external landscaping. Those belong to the finishing stage.
The grey area, and the place where quotations differ most, is plumbing and electrical. Some contractors include the pipes and conduits in the grey rate. Others price them separately as "services." One quote of Rs 3,000 per sq ft that excludes services can be more expensive than a Rs 3,300 quote that includes them, so always ask for the scope in writing.
Prices differ by city because of freight, local labour supply, soil conditions, approval rules and the society's own inspection requirements. Here is what we are seeing.
Islamabad is consistently the most expensive of the three big markets. A standard A-grade double-storey house in the twin cities is being quoted at roughly Rs 3,200 to Rs 3,600 per sq ft with material in Q4 2026. Builder rate cards put the "standard" Islamabad and Rawalpindi grey rate around Rs 3,500, about Rs 200 above Lahore. DHA Islamabad is quoted higher, at around Rs 3,700 for standard specification, and upper-specification work with basements can run well past Rs 4,000.
There are three reasons the capital costs more. First, subsoil in much of Islamabad and Rawalpindi is mixed and in places rocky, which means slower excavation and heavier foundation work. Second, labour is dearer, with labour-only rates running about Rs 150 per sq ft above Lahore. Third, CDA and RDA approval requirements, along with society-level inspections, add time and compliance cost.
If you are browsing plots and thinking about how much the house will really cost on top, real estate in Islamabad on Milkiyat is a good place to compare plot prices against what you will spend building. Rawalpindi buyers can start from the Rawalpindi city page.
Societies matter too. Gated communities such as Bahria Enclave, DHA Gandhara, Gulberg Greens and Margalla Enclave each have their own building bylaws, approval fees, completion timelines and mandatory inspections. Some contractors quote slightly lower in certain societies and noticeably higher in others, so a rate you hear for "Islamabad" is only a starting point.
Lahore is the most transparent market, partly because so many builders publish their rate cards. In October 2026, builder-published rates for grey structure with material cluster between Rs 2,800 and Rs 3,500 per sq ft. One Lahore contractor's October 2026 update estimates Rs 3,000 to Rs 3,250 per sq ft, which would put a 1,900 sq ft house at roughly Rs 57 to Rs 62 lakh. Another Q4 2026 rate card lists the standard A-grade rate at Rs 3,300 in LDA areas and about Rs 3,500 in DHA Lahore.
Society premiums are real but not enormous. Contractors report that DHA Lahore adds roughly 15 to 18 percent over open LDA areas because of slab inspections and the requirement to use a registered architect, while Bahria Town Lahore adds a smaller premium for its approval process. If you are comparing plots across the city, the Lahore city page on Milkiyat will help you weigh plot price against building cost.
Karachi's grey structure rates have historically sat a little below Islamabad and close to Lahore. Milkiyat's mid-2026 tracking placed Karachi between Rs 2,650 and Rs 3,200 per sq ft; since then rising material costs have nudged typical quotes toward Rs 2,900 to Rs 3,500 per sq ft. One city-adjustment model puts Karachi about 2 percent above Lahore on the same specification, which is consistent with that range.
Premium areas behave differently. In DHA Karachi and Clifton, builders regularly quote Rs 3,500 to Rs 4,000 per sq ft for premium specifications, mainly because of strict engineering supervision, higher labour rates and the cost of moving materials into dense neighbourhoods. Karachi also depends heavily on local cement supply, so cement prices there can differ from the north by a noticeable margin. If you are weighing where to buy or build in Sindh's capital, start with the Karachi city page.
| City | Typical grey structure rate with material | Premium areas | Main cost driver |
|---|---|---|---|
| Islamabad / Rawalpindi | Rs 3,200 – 3,600 | DHA, upper-spec: Rs 3,700 – 4,200+ | Soil, labour, approvals |
| Lahore | Rs 2,800 – 3,500 | DHA Lahore: about Rs 3,500+ | Society inspections, steel grade |
| Karachi | Rs 2,900 – 3,500 | DHA, Clifton: Rs 3,500 – 4,000 | Supervision, logistics, cement supply |
When a contractor quotes a "grey structure rate with material," or what many call a grey structure contract rate with material, they are quoting a single all-in price per sq ft. It covers the contractor's materials, labour, tools, shuttering, site supervision and their margin. In other words, you hand over your drawings, pay in stages and receive a finished shell.
The advantages are clear. You have one party responsible for schedule and quality, you are shielded from daily price swings once the contract is signed, and you do not have to manage a store, a steel yard and a truck of bricks. The risks are equally clear. If the specification is vague, the contractor may use cheaper steel or leaner concrete mixes and you will not see it. This is why the written scope matters more than the rate itself.
A solid with-material quotation should state, at minimum:
In a labour-only grey structure contract, you buy all the materials yourself and pay the contractor only for workmanship. The contractor's team handles masonry, steel fixing, shuttering, concreting, plastering and curing. This is also called "mistri contract," "labour contract" or "labour rate."
In Lahore, labour-only grey structure rates in 2026 are being quoted between about Rs 450 and Rs 850 per sq ft, with the narrower, more realistic band for a standard house at Rs 550 to Rs 800. Some builder rate cards put site labour for standard grey structure at Rs 650 to Rs 850. Islamabad and Rawalpindi sit about Rs 150 per sq ft higher, so you should plan for roughly Rs 700 to Rs 1,000. For Karachi, labour-only quotes are broadly in line with Lahore, though you should confirm locally because the supply of skilled shuttering and steel-fixing crews varies by area.
As a quick sanity check, labour-only grey structure is typically about one-fifth of the with-material rate. If someone quotes you Rs 1,500 for labour-only on a standard house, something is off. If someone quotes Rs 350, ask who is checking the quality.
| Plot size (typical covered area) | Labour-only at Rs 600 / sq ft | Labour-only at Rs 800 / sq ft |
|---|---|---|
| 5 marla (about 1,900 sq ft) | Rs 11.4 lakh | Rs 15.2 lakh |
| 7 marla (about 2,500 sq ft) | Rs 15.0 lakh | Rs 20.0 lakh |
| 10 marla (about 3,300 sq ft) | Rs 19.8 lakh | Rs 26.4 lakh |
| 1 kanal (about 6,000 sq ft) | Rs 36.0 lakh | Rs 48.0 lakh |
| With material (contractor supplies) | Labour only (owner supplies) | |
|---|---|---|
| Price per sq ft | Higher, includes contractor margin | About one-fifth of the full rate |
| Your effort | Low, one point of contact | High, you manage purchasing and storage |
| Cost control | Fixed once signed | Can save money if you buy well, can lose it through wastage and theft |
| Quality risk | Hidden substitution of materials | Lower, because you see what goes in, but workmanship still needs checking |
| Best for | Owners abroad, busy professionals, first-time builders | Owners who live near the site and can supervise daily |
Many owners choose a hybrid: they buy steel and cement directly, where price and brand are easy to verify, and let the contractor supply bricks, sand, crush and shuttering. This keeps the biggest-ticket, easiest-to-substitute items in your hands without making you run the whole site.
People often ask for the cost per marla, but a marla is a land measure, not a building measure. What you pay for is the covered area, which depends on the number of floors, whether you build a basement, and how much of the plot you cover. A double-storey house on a 5 marla plot typically has around 1,900 to 2,200 sq ft of covered area, while a double-storey 10 marla house is often about 3,300 sq ft or more. If you need to convert between marla, kanal and square feet for your plot, the Milkiyat Area Unit Converter saves guesswork.
The table below applies three planning rates to common covered areas. Rs 3,000 is a lean-but-realistic with-material rate for Lahore and Karachi. Rs 3,300 is a standard rate. Rs 3,600 is where Islamabad and better-specification homes often land.
| Plot size | Assumed covered area | At Rs 3,000 / sq ft | At Rs 3,300 / sq ft | At Rs 3,600 / sq ft |
|---|---|---|---|---|
| 5 marla | 1,900 sq ft | Rs 57.0 lakh | Rs 62.7 lakh | Rs 68.4 lakh |
| 7 marla | 2,500 sq ft | Rs 75.0 lakh | Rs 82.5 lakh | Rs 90.0 lakh |
| 10 marla | 3,300 sq ft | Rs 99.0 lakh | Rs 108.9 lakh | Rs 118.8 lakh |
| 1 kanal | 6,000 sq ft | Rs 1.80 crore | Rs 1.98 crore | Rs 2.16 crore |
Two cautions. First, these figures are for the grey structure only. Second, if your plan includes a basement, budget for it separately; basement grey work is priced per sq ft of basement area at a higher rate than above-ground work, with Islamabad quotes in the range of Rs 4,200 to Rs 4,500 for standard basement work in recent rate cards.
If you want the full cost of a complete house on specific plot sizes, Milkiyat's 5 marla house construction cost guide for Islamabad, Pindi and Lahore and the 20 marla house construction cost breakdown go size by size.
Grey structure is a material-heavy job. A rough but useful rule is that cement and steel together form the largest share of the with-material rate, followed by bricks or blocks, sand and crush, shuttering, and labour. These are the late-2026 market ranges we are working with:
To see how these translate into your rate, take a common contractor rule of thumb: a standard house needs about 3.5 to 4.5 kg of steel and roughly 0.4 to 0.5 bags of cement per sq ft of covered area. At current prices, that is about Rs 900 to Rs 1,250 for steel and Rs 560 to Rs 775 for cement, or somewhere around Rs 1,500 to Rs 2,000 per sq ft for these two items alone, before bricks, aggregate, shuttering, labour and margin. Public bulk-material estimates for Lahore in September 2026 put the combined cost of major bulk materials at roughly Rs 1,479 to Rs 2,506 per sq ft, which fits this picture. These quantities are rules of thumb, so your structural engineer's bill of quantities is the authority for your project.
Why does this matter? Because when steel or cement moves by 10 percent, your grey structure cost moves by a meaningful amount. If you sign a fixed with-material contract during a price spike, you may overpay; if you sign before a spike, you are protected. Watching the weekly price movement is worthwhile, and the Pakistan Bureau of Statistics publishes weekly price data you can check yourself.
A common budgeting mistake is to plan only for the grey structure and discover later that finishing costs as much again, or more. In 2026, grey structure forms roughly 40 to 50 percent of a complete standard house, depending on how heavy the finishing is. Builder rate cards put the grey structure share at about 44 percent at standard specification in Lahore.
| Stage | Lahore (typical, per sq ft) | What it covers |
|---|---|---|
| Grey structure with material | Rs 2,800 – 3,500 | Foundation, RCC frame, masonry, plaster, rough services |
| Finishing on top | Roughly Rs 2,500 – 4,500+ | Tiles, paint, woodwork, doors and windows, fixtures, fittings, electrical finishing |
| Complete standard house (turnkey) | Rs 5,000 – 7,500 | Depends on finishing grade; mid-range and premium finishes push it higher |
The spread in turnkey rates is wide because finishing is where owners' choices diverge: imported versus local tiles, solid wood versus engineered doors, standard fittings versus branded ones. In Islamabad and Rawalpindi, a complete standard house is being planned at around Rs 7,900 per sq ft in some builder rate cards, compared with about Rs 7,500 in Lahore.
The practical lesson: decide your target finishing level before you finalise the grey structure, because it affects structural decisions like slab thickness for heavy flooring, wall thickness for sound insulation and conduit layouts. For a longer breakdown of the full cost, see our construction cost crisis analysis for 2026.
Owners are often surprised when an online calculator shows a figure noticeably below their contractor's quote. For example, a calculator may show a 10 marla house with grey structure material cost of about Rs 74 lakh plus a share of labour, while a contractor quotes close to Rs 1 crore or more for the same shell. This does not automatically mean the contractor is overcharging. Calculators build a rate from a standard basket of materials at average prices. A real quote includes supervision, wastage, equipment, transport to your specific site, dealer premiums at the moment of purchase, the contractor's overhead and profit, and any society-specific requirements.
The right way to use a calculator is as a floor and a conversation starter. Take the calculator output, add a realistic allowance for the factors above, and compare it with at least three written quotes. If one quote is far below the rest, find out which scope item is missing before you celebrate.
Several factors move the rate per sq ft, and knowing them helps you negotiate fairly rather than only hunting for the lowest number.
Location and society. DHA-type societies with mandatory inspections, registered architects and approval charges cost more than open-market plots. Remote sites cost more because of transport.
Soil condition. Weak or rocky soil needs deeper or wider foundations, special excavation, or a soil investigation report. In parts of Islamabad and Rawalpindi this is a regular cost driver.
Number of floors and basement. A basement is priced separately and at a higher rate. Additional storeys increase the structural load, so columns and foundations are heavier even before you count the extra area.
Design complexity. Large spans, cantilevers, double-height ceilings, curved walls and heavy elevations add steel and shuttering. A simple rectangular plan is the cheapest to build.
Steel and cement choice. Grade 60 steel from a recognised mill and major-brand cement cost more than unbranded alternatives but give you documented quality. This is not the place to economise blindly.
Season and timing. Summer, with high demand and heat, can push prices up. Several market observers note that buying in the November to February period can bring better rates. If you have flexibility, plan your major purchasing around that window.
Labour market. Skilled shuttering carpenters, steel fixers and masons are in demand in boom periods. A good contractor with an established crew may charge more and still save you money by avoiding rework.
Whether you choose material or labour-only, put it in writing. Here is a practical checklist.
A sample progress-based schedule many owners find reasonable for a with-material contract is to split payments across foundation completion, ground-floor slab, first-floor slab, masonry and plaster, with a small final retention. The exact percentages should be negotiated and recorded in your agreement.
Let us run the numbers for a 10 marla double-storey house in Islamabad with about 3,300 sq ft of covered area.
Now consider the other side of the same house on a labour-only basis. At Rs 800 to Rs 1,000 per sq ft of labour in Islamabad, labour comes to about Rs 26 to Rs 33 lakh. You would then buy the materials yourself, with a budget that depends on your purchasing discipline and on how stable prices remain.
Remember that none of this includes finishing, the boundary wall and gate, a septic tank and water tank if priced outside the rate, utility connections, architect and engineer fees, or society approval charges. List these separately before you start. If you plan to finance part of the project, the Milkiyat Home Loan Calculator can show you what the monthly commitment looks like.
For many families, building is the cheaper route to the exact home they want. For others, once you add plot cost, grey structure, finishing, contingency, time and stress, a ready house or apartment is the better value. It is worth running both numbers before you commit.
If you are still shopping for land, look at plots in developed societies and compare the combined plot-plus-construction cost against ready homes in the same area. On Milkiyat you can browse plots for sale in Islamabad and houses for sale in Islamabad, and check apartments for sale in Islamabad if a smaller, ready-to-move option suits your budget.
Housing societies are a good example of how this comparison works in practice. In Park View City Islamabad, you can look at plots for sale, price in a grey structure and finishing budget using the figures in this guide, and then compare the total with apartments for sale in Park View City. If the numbers for building are close to the cost of a ready apartment, convenience may tip the decision. Whichever society you choose, check the society's own building rules, approval process and any construction deadlines with its management before you commit to a contractor.
If you would rather get advice from someone on the ground, you can browse verified property agents on Milkiyat or look through agencies. A local agent who knows the society can tell you which blocks have better soil, which streets have easier access for material trucks, and what recent buyers have actually paid to build. For newly launched developments, the new projects page is also worth a look.
In late 2026, a realistic planning range for grey structure in Pakistan's three largest markets is about Rs 2,800 to Rs 3,500 per sq ft with material, with Islamabad and DHA-type societies at the top and labour-only contracts costing roughly Rs 550 to Rs 850 (higher in the twin cities). The number that matters most, however, is not the rate on its own but the scope behind it. Fix the drawings, the materials, the payment milestones and the exclusions before you sign, keep a contingency, and verify rates again close to your start date because steel and cement can move quickly.
Start with the Milkiyat Construction Cost Calculator for a quick estimate, use the figures above to test any quotation you receive, and if you are still choosing between building and buying, explore listings across Islamabad and talk to a local agent who can show you real numbers from your target area.
With material, the grey structure rate is roughly Rs 2,800 to Rs 3,500 per sq ft of covered area across Lahore, Karachi and Islamabad in late 2026. Islamabad and Rawalpindi are typically Rs 3,200 to Rs 3,600, and premium societies or upper specifications can go higher.
Standard A-grade grey structure with material in Islamabad and Rawalpindi is being quoted at about Rs 3,200 to Rs 3,600 per sq ft, with DHA Islamabad around Rs 3,700 and upper-specification or basement work above Rs 4,000. Labour-only contracts run about Rs 700 to Rs 1,000 per sq ft.
In Lahore, builder-published rates for grey structure with material cluster between Rs 2,800 and Rs 3,500 per sq ft, with a standard A-grade rate of around Rs 3,300 and DHA Lahore at about Rs 3,500. Labour-only rates are generally Rs 550 to Rs 850 per sq ft.
Typical Karachi quotes fall around Rs 2,900 to Rs 3,500 per sq ft with material, while DHA Karachi and Clifton premium work is quoted at roughly Rs 3,500 to Rs 4,000.
For labour-only grey structure, expect roughly Rs 550 to Rs 850 per sq ft in Lahore and Karachi, and about Rs 150 more in Islamabad and Rawalpindi. This is typically around one-fifth of the with-material rate.
For a 10 marla house with about 3,300 sq ft of covered area, labour-only comes to around Rs 19.8 to Rs 26.4 lakh at Rs 600 to Rs 800 per sq ft. Add the cost of all materials, which you purchase separately.
Cost per marla depends on covered area. For a double-storey house, a 5 marla plot with about 1,900 sq ft typically needs about Rs 57 to Rs 68 lakh for grey structure at Rs 3,000 to Rs 3,600 per sq ft, while a 10 marla house with about 3,300 sq ft needs roughly Rs 99 to Rs 119 lakh.
Grey structure covers excavation, foundations, RCC columns, beams and slabs, brick or block masonry, staircase structure, plaster and usually rough electrical conduits and plumbing lines. Tiling, paint, doors, windows, fixtures and cabinets belong to finishing. Always confirm in writing whether services are included.
In a standard house, grey structure is roughly 40 to 50 percent of the total cost, so finishing is often equal to or greater than the structure itself, especially with premium materials. Plan the finishing budget before you start construction.
Grey structure ka rate 2026 mein material ke saath taqreeban Rs 2,800 se Rs 3,500 per sq ft hai, jabke sirf labour ka rate Rs 550 se Rs 850 per sq ft ke qareeb hai. Islamabad aur Rawalpindi mein rate thoda zyada hota hai, aur DHA jaisi societies mein aur bhi zyada.
Choose with-material if you want a single point of responsibility and cannot supervise daily. Choose labour-only if you live near the site, can buy materials carefully and want direct control over quality. Many owners buy steel and cement themselves and leave the rest to the contractor.
Calculators use average material baskets, while contractors price supervision, wastage, transport, society requirements and their own margin. Treat calculator output as a starting point and compare at least three written quotes with the same scope.
Most owners keep 10 to 15 percent above the quoted figure to cover price movement, design changes and unforeseen soil or site conditions.